17ECTOR <br /> ENGINEERING INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Daily Field Report Sequence Number: <br /> Forward Landfill 021605.03 38 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Manteca,Ca Butch Stefan Forward, Inc. October 21,2003 Tuesday <br /> General Contractor: Liner Contractor: Project Engineer: <br /> Sukut Construction GSE San Beta Lewis <br /> General Foreman: Liner Superintendent: Other: <br /> David Hasal <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> On site native, light brown silty CLAY Hot, clear and Ken Davila <br /> breezy <br /> Equipment on site: <br /> I-D6 dozer, 1-water truck, 1-DS dozer, 1-633 scra er, 1-16G blade <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> I arrived on site today for testing and observations at the location listed above. The foreman for Sukut was <br /> grade setting in the morning so we couldn't discuss the day's plan of operation. Sukut Construction <br /> continued the earthworks operations with the 16G blade and D5 dozer cutting the east FU-03 cell floor area <br /> and the scraper hauling the excess cut material to the stockpile. In the afternoon,the blade moved to the <br /> north cell floor and the D5 moved back to cutting the desilting basin's north slope. The D6 dozer continued <br /> cutting the north and east slopes of the leachate pond. Sukut's surveyors were on site today to plot points on <br /> the cell floor and various other locations. <br /> Review of the certifications and an on site check-in of geocomposite began and will continue throughout <br /> the day. At shift's end,all rolls of geocomposite had been accounted for and were logged in. On site lab <br /> testing of the clay material continued with the set up of two(2)Atterberg limits and two sieve analyses <br /> (gradations). Both were left to soak overnight as per ASTM standards. <br /> Photos of the grading operations at the various work areas were taken in the morning. <br /> Adak <br /> Prepared By: Reviewed By: <br /> 4/23/03,Rev. 0 1 of 1 <br /> r-,) <br />