VCYTOR <br /> NGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Daily Field Report Sequence Number: <br /> Forward Landfill 2008 021605.08 52 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Manteca, CA Forward/AWI Au ust 29, 2008 Friday <br /> General Contractor: Liner Contractor: Project Engineer: <br /> Guinn Comanco Lewis Engineering <br /> General Foreman: Liner Superintendent: Other: <br /> -Larry Jose Ramirez <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> On-Site light tan clayey soil warm and breezy Aaron Lickingteller <br /> Equipment on site: <br /> 815 compactor,tractor with BeGe blade and disc,5 x 637 scrapers, 1 x 627 scraper,2 x water trucks,D-6 dozer,D-6 dozer <br /> w/slo e-board,excavator,623 scra er, 16 G Motograder,825 compactor,smooth drum roller,backhoe,2 forklifts <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> - Comanco installed 113,116 square feet of 12 oz. geotextile on the middle portion of the cell floor, <br /> including the middle sump. <br /> - Vector and Comanco personnel inspected the HDPE geomembrane for damages prior to installation <br /> of 12 oz. geotextile. <br /> - Guinn began installation of 6 inch diameter pipe, a second 12-oz. geotextile cushion, and gravel in the <br /> southeast portion of the LCRS ditch. <br /> - Due to an excessive amount of damaged sandbags, Comanco had to sweep the dirt from the LCRS <br /> ditches. <br /> - Comanco personnel made two repairs on the liner and conducted non-destructive vacuum testing on <br /> them. <br /> Prepared By: Reviewed By: <br /> 4/23/03,Rev.0 1 of 1 <br /> C-2 <br />