T/E "TOR <br /> ENGINEERING,INC. <br /> DAILY CONSTRUCTION FIELD REPORT <br /> Project Name: Project No. Daily Field Report Sequence Number: <br /> Forward Landfill 2008 021605.08 53 <br /> Location of Work: Client Or Manager Date: Day of The Week: <br /> Manteca, CA Forward/AWI Au ust 30, 2008 Saturday <br /> General Contractor: Liner Contractor: Project Engineer: <br /> Guinn Comanco Lewis Engineering <br /> General Foreman: Liner Superintendent: Other: <br /> Larry Jose Ramirez <br /> Source and Description of Fill Material: Weather: CQA Technician: <br /> On-Site light tan clayey soil warm and breezy Aaron Lickingteller <br /> Equipment on site: <br /> 815 compactor,tractor with BeGe blade and disc,5 x 637 scrapers, 1 x 627 scraper,2 x water trucks,D-6 dozer,D-6 dozer <br /> w/slope-board,excavator,623 scraper, 16 G Motograder,825 compactor,smooth drum roller,backhoe,2 forklifts <br /> NOTES(Describe work completed during the day,any problems and their solutions): <br /> - Comanco installed 83,160 square feet of 12 oz. geotextile on the northern half of the cell floor, <br /> including the northern sump. <br /> - Vector and Comanco personnel inspected the HDPE geomembrane for damages prior to installation <br /> of 12 oz. geotextile. <br /> Comanco ended up short approximately 11,200 square feet in area of 12 oz. geotextile. Sangeeta <br /> Lewis was contacted to see if modifications to the design could be completed using geocomposite <br /> existing on site. Sangeeta insisted that geocomposite not be used and that more 12 oz. geotextile be <br /> used due to stability issues. <br /> Prepared By: Reviewed By: <br /> 4/23/03,Rev.0 1 of 1 <br /> C-2 <br />