1.7 Water Level Measurement <br /> • The elevation reference point at the well location and the ground surface elevation <br /> will be surveyed within 0.01 foot. <br /> • Method and time of water level measurement will be recorded in daily field logs. <br /> 1.8 Proposed Schedule for Work <br /> • Submittal of Work Plan-early September 2015 <br /> • Approval of Work Plan (RWQCB)-Sept.2015 <br /> • Installation of monitoring well-late Sept.2015 <br /> • Monitor and sample monitoring well-early Oct.2015 <br /> • Monitoring Well Installation Report-Oct.2015 <br /> • Quarterly/Semi-Annual Monitoring Report-Oct.30th 2015 <br /> 3 <br /> Well Installation Workplan Stockton,Ca <br /> Cove Contractors,Inc. Project No.04.20090407.00 <br />