Laserfiche WebLink
24 March 2014 Environmental <br /> Page 7 Resources <br /> Management <br /> SCHEDULE <br /> We are prepared to implement the scope of services described above <br /> immediately upon receipt of notice to proceed. Actual schedule dates <br /> may be determined based on subcontractor,vendor, and staff <br /> availability. The proposed general schedule of activities is provided <br /> below. <br /> CWA Approval 4/1/14 <br /> Preparation for field work 4/1/14 -4/11/14 <br /> Conduct field work 4/14/14-4/18/14 <br /> Receive laboratory data 5/2/14 <br /> Prepare documentation report 5/5/14 -5/16/14 <br /> Sincerely, <br /> John Moe, P.E. Jim Warner, P.G. <br /> Project Manager Principal-in-Charge <br /> Attachments: <br /> Attachment 1 Figures: <br /> Figure 1 Site Location Map <br /> Figure 2 Proposed Boring Locations- North Compressor Station <br /> Figure 3 Proposed Boring Locations-South Compressor Station <br />