Laserfiche WebLink
Page 1 of 4 <br /> Natalia Subbotnikova [EH] <br /> From: Natalia Subbotnikova [EH] <br /> Sent: Friday, November 14, 2008 3:56 PM <br /> To: 'Yekta, Gino' <br /> Subject: RE: CHSL-LFG Ext Well Installation -Project Schedule <br /> Hi Gino, <br /> I was planning to go to Corral Hollow on Monday (11/17/08)anyways.So, I will meet you at my office around <br /> 10:00 am to go to the site. <br /> Have a wonderful weekend. <br /> Thanks..... Natalia <br /> From: Yekta, Gino [mailto:GYekta@CIWMB.ca.gov] <br /> Sent: Friday, November 14, 2008 3:10 PM <br /> To: Natalia Subbotnikova [EH] <br /> Subject: RE: CHSL-LFG Ext Well Installation -Project Schedule <br /> Hi Natalia: I was wondering whether you might have time on Monday (11/17/08) to go to Corral Hollow. <br /> If you do, I'll meet you at your office around 10:00 to go to the site. Please let me know at your <br /> convenience if you have time. Thanks...............Gino <br /> From: Natalia Subbotnikova [EH] [nsubbotnikova@sjcehd.com] <br /> Sent: Wednesday, November 12, 2008 4:07 PM <br /> To: Yekta, Gino <br /> Subject: FW: CHSL-LFG Ext Well Installation -Project Schedule <br /> FYI..... <br /> Thanks..... Natalia <br /> From: Joyesh Chandra [mailto:Jchandra@sjgov.org] <br /> Sent: Wednesday, November 12, 2008 2:45 PM <br /> To: Natalia Subbotnikova [EH] <br /> Cc: Robert McClellon [EH]; Michael Carroll; Jaime Perez; Billy Baier; Ifgc97@aol.com <br /> Subject: CHSL-LFG Ext Well Installation -Project Schedule <br /> Hello Natalia <br /> Thank you for faxing the approved well permit permits for the Landfill Gas (LFG) extraction well <br /> installation project at our Corral Hollow Landfill. Per our phone conversation, Solid Waste <br /> Division's contractor, LFG Control Inc, will begin the project on November 17, 2008. There are <br /> minor changes in the order of work the Contractor will perform due to the availability of his drill <br /> rig. The contractor has planned the following work schedule: <br /> (Working Days: Monday to Friday lam to Spm) <br /> 1. Nov 17: <br /> Site preparation: Drill rig pads will be built near hard to access drilling locations. <br /> 11/14/2008 <br />