• . Page 2 of 4 <br />Division's contractor, LFG Control Inc, will begin the project on November 17, 2008. There are <br />minor changes in the order of work the Contractor will perform due to the availability of his drill <br />rig. The contractor has planned the following work schedule: <br />(Working Days: Monday to Friday 7am to 5pm) <br />1. Nov 17: <br />Site preparation: Drill rig pads will be built near hard to access drilling locations. <br />2. Nov 18th -24th <br />a. Excavation of well Lateral trenches <br />b. Installation of well lateral pipes <br />c. Backfill of lateral trenches (Tentative) <br />d. Lateral/Header connection (Tentative) <br />3. Nov 24th <br />Drilling of the LFG wells will tentatively begin on November 24th. The drill rig crew may <br />take two to four hours to drill a well. Well construction will begin immediately after <br />drilling. <br />4. Nov 27th and Nov 28th <br />Thanksgiving holiday <br />5. Dec 9th <br />Construction completion <br />Inspection of all work will be coordinated with you per the project's work plan. The contractor <br />has been notified regarding EHD's inspection schedule (9 am to 3.30 pm, M -F). <br />Please let me know if you need any additional information. <br />Thanks <br />JOYESH J CHANDRA <br />SAN JOAQUIN COUNTY <br />DEPARTMENT OF PUBLIC WORKS <br />SOLID WASTE DIVISION <br />PH -(209)468-3066 <br />FAX -(209)468-3078 <br />From: 3oyesh Chandra <br />Sent: Friday, October 31, 2008 3:01 PM <br />To: 'Natalia Subbotnikova [EH]' <br />Cc: Michael Carroll; Robert McClellon; 'GYekta@CIWMB.ca.gov' <br />Subject: RE: CHSL-LFG Ext Well Installation -Project <br />Hello Natalia <br />Attached, please find the amended work plan for the two additional Landfill Gas (LFG) <br />11/19/2008 <br />