Tentative Project Schedule <br /> Arcady Disposal Site <br /> Holt, California <br /> ID Task Name Duration Start Finish May June July AugustI Septe I Octobel Noveml Decem Januar Febru March <br /> 1 RWQCB&DTSC Letter(sent on 6/5) 4 days Tue 05/30/00 Fri 06/02/00 <br /> 2 VCP Agreement(submitted on 6/22) 55 days Mon 06/05/00 Fri 08/18/00 <br /> 3 Develop SOW with RWQCB 15 days Mon 06/05/00 Fri 06/23/00 <br /> 4 Internal Admin.(ERM&Bright and Brown) 40 days Mon 06/26/00 Fri 08/18/00 <br /> 5 Draft Workplan 10 days Mon 08/21/00 Fri 09/01/00 <br /> 6 Regulatory Review 15 days Mon 09/04/00 Fri 09/22/00 <br /> 7 Final Workplan 10 days Mon 09/25/00 Fri 10/06/00 <br /> 8 Field Work 80 days Mon 10/09/00 Fri 01/26/01 <br /> 9 Preparation 10 days Mon 10/09/00 Fri 10/20/00 <br /> 10 Soil Investigation 5 days Mon 10/23/00 Fri 10/27/00 <br /> 11 Well Installlation&1st Sampling Event 20 days Mon 10/30/00 Fri 11/24/00 <br /> 12 2nd Sampling Event 20 days Mon 01/01/01 Fri 01/26/01 <br /> 13 Surface Water Sampling 5 days Mon 12/11/00 Fri 12/15/00 , <br /> 14 Summary Report and Risk Evaluation 20 days Mon 01/29/01 Fri 02/23/01 <br /> 15 1 Regulatory Review&Negotiation 20 days Mon 02/26/01 Fri 03/23/01 <br /> Page 1 <br />