/ <br /> <br /> <br /> <br /> <br />k9 KLEIN FELDER <br />4 ANTICIPATED SCHEDULE <br />The following project schedule is applicable for the proposed scope of work. The following <br />table outlines the abandonment and re-installation tasks for the damaged well. <br />Approximate <br />Timeline <br />Task <br />Week 0-2 Workplan Submittal to RWQCB for review* <br />Week 2-4 Permitting and pre-field scheduling* <br />Week 4 Monitoring well abandonment and re installation** <br />Week 6 Report Preparation and Submittal to Client <br />*Kleinfelder has no control over the time required by a regulatory agency to review and approve <br />a workplan and permit applications. <br />**Kleinfelder has no control over the time required or time frame that subcontractors place on <br />the outlined tasks. <br />24134.EO I / STO3R304 Page 7 of 10 <br />Copyright 2003, Kleinfelder, Inc. February 26, 2003