TERRAX <br />Environmental Engineering and Consulting <br />5.0 Estimated Schedule <br />The work is likely to take at least 2 weeks to complete. <br />Activity Time <br />Permit application and work plan 1 day <br />Permit approval 10 working days <br />Site works 1 day <br />Terrax will not be responsible for delays caused by other forces outside of Terrax's control; this <br />includes but is not limited to permit approvals, drillers and laboratory availability delays. <br />Andrew Brack <br />Principal Date <br />4952 Warner Avenue, Suite 242, Huntington Beach California, 92649 Page 5