Soil Boring Results and VEG/ISCO Work Plan <br />Field Maintenance Shop #24, Stockton, California October 2016 <br />final schedule will depend on the CVRWQCB approval of the work plan and VEG/ISCO contractor <br />availability. A tentative schedule for all site activities is summarized below. <br />Task Estimated Date <br />Work Plan Approval and Permitting September 2016 <br />Utility location prior to VEG Well Installations September 2016 <br />VEG Implementation September-October 2016 <br />ISCO Injections November 2016 - 1 week after VEG <br />implementation <br />30-day post-ISCO sampling event 30 days after ISCO injections <br />Post-ISCO Waste Pickup Event 1 Within 45 days of completion of field activities <br />30-day MRP Report to the RWQCB 60 days from 30-day MRP sampling event <br />90-day post-ISCO sampling event 90 days after ISCO injections <br />Post-ISCO Waste Pickup Event 2 Within 45 days of completion of field activities <br />90-day MRP Report to the RWQCB 60 days from 90-day MRP sampling event <br />180-day post-ISCO sampling event 180 days after ISCO injections <br />Post-ISCO Waste Pickup Event 2 Within 45 days of completion of field activities <br />180-day MRP Report to the RWQCB 60 days from 180-day MRP sampling event <br />Meeting with CVRWQCB regarding site <br />closure evaluation <br />After completion of sampling events and <br />reporting, prior to submittal of Annual Report <br />Annual Remedial Action Progress Report to <br />RWQCB <br />270 Days after ISCO injections <br />Page 12 •