Commissioning Plan, June 24, 2015 <br />Preliminary Commissioning Schedule <br />o Equipment is not "temporarily" started (for heating or cooling), until pre -start checklist <br />items and all manufacturer pre -start procedures are completed and moisture, dust and <br />other environmental and building integrity issues have been addressed. <br />o Functional Testing does not begin until pre -functional, start-up and TAB is completed for <br />a given system. <br />o The controls system and equipment it controls are not Functionally Tested until all points <br />have been calibrated and pre -functional checklists are completed. <br />Commissioning Activity Duration Estimated Estimated <br />Start Date Completion Date <br />BOD <br />Commissioning Plan <br />Preliminary Commissioning Plan <br />Scoping Meeting <br />Final Commissioning Plan <br />Submittals and test writing <br />Review Mechanical submittals <br />Identify Startup and pre -functional <br />checklists <br />DDG pFogFam review meeting (N/A) <br />Write Functional Tests <br />Construction Observation <br />Site observations <br />HVAC pre -functional checklist <br />completion <br />Equipment startup <br />Startup documentation <br />Controls system checkout <br />Test and Balance <br />TAB air side <br />TAO wateF side (N/A) <br />HVAC Functional performance testing <br />Substantial Completion <br />Post Acceptance Phase <br />Owner move -in <br />Short-term diagnostic monitoring <br />O&M, training, reporting, warranty <br />O&M Manuals submitted <br />Review O&M manuals <br />Review as -built documentation <br />Seasonal testing <br />Final commissioning report <br />8of8 <br />