My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
WORK PLANS
EnvironmentalHealth
>
EHD Program Facility Records by Street Name
>
Y
>
YOSEMITE
>
750
>
1600 - Food Program
>
PR0161533
>
WORK PLANS
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
12/20/2021 7:17:05 PM
Creation date
10/15/2021 3:39:59 PM
Metadata
Fields
Template:
EHD - Public
ProgramCode
1600 - Food Program
File Section
WORK PLANS
RECORD_ID
PR0161533
PE
1632
FACILITY_ID
FA0001342
FACILITY_NAME
MUSD-LINCOLN SCHOOL
STREET_NUMBER
750
Direction
E
STREET_NAME
YOSEMITE
STREET_TYPE
AVE
City
MANTECA
Zip
95336
APN
22118001
CURRENT_STATUS
01
SITE_LOCATION
750 E YOSEMITE AVE
P_LOCATION
04
P_DISTRICT
005
QC Status
Approved
Scanner
SJGOV\jcastaneda
Tags
EHD - Public
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
2850
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
PROGRESS SCHEDULES <br />Section 01310 <br />15-1207 <br />PART 1 - GENERAL <br />1.01 INCLUSION OF OTHER CONTRACT DOCUMENTS <br />A. The General Conditions, Supplementary Conditions and Division 1 are fully applicable to this <br />Section, as if repeated herein. <br />1.02 GENERAL STATEMENT <br />A. It is the intent of this specification to provide a means by which to insure timely completion of <br />the Work of the Contract. <br />B. The Contractor shall be responsible for planning, scheduling and reporting the progress of <br />the Work. Planning, scheduling and reporting will incorporate the input of the various <br />Subcontractors, Suppliers, Manufacturers, etc., that are responsible to the Contractor of the <br />Work. <br />C. This Schedule is defined as the network diagram, or diagrams and includes the various <br />reports, narratives and charts required by this specification. Each is considered to be part of <br />the Schedule. Submittal of one without the other shall constitute non-compliance of contract <br />requirements unless previously approved or directed by the Architect in writing. <br />D. Float or slack time is not for the exclusive use or benefit of either the Owner or the <br />Contractor, but is a resource available to both parties. To this end it is considered both <br />responsible and reasonable that the schedule contain no more than fifteen (15) percent of <br />the activities to be critical or near -critical. Near -critical is defined as float or slack time for <br />one (1) to ten (10) work days. <br />E. The schedule shall be submitted within fifteen (15) calendar days after the date of the Notice <br />to Proceed (Start Letter) and shall include a complete critical path schedule with detailed <br />network diagrams or sub -network diagrams for all the work. Interdependencies between the <br />various detailed network diagrams shall be clearly indicated. <br />F. The schedule shall include the following features: <br />1. Each diagram shall show the activities, order and interdependence of the activities, <br />and the sequence of work, as planned by the Contractor. <br />2. The Schedule shall include, in addition to construction activities, such tasks as <br />mobilization, demobilization, submittal, and approval of samples of materials and shop <br />drawings, procurement of significant materials and equipment, fabrication of special <br />items as well as installation and testing. <br />3. The Activities shall be described and organized so as to conform to the Payment <br />Schedule. <br />G. Upon the Architect's request, the Contractor shall participate in the review and evaluation of <br />his submissions. Any revisions deemed necessary or desirable as a result of this review <br />shall be resubmitted within ten (10) calendar days after the review. The Schedule, as <br />revised, shall be used by the contractor for planning, organizing, and directing the work and <br />for reporting of progress. <br />H. Acceptance by the Owner and/or Architect of the reasonableness of the Contractor's <br />scheduling and cost allocations shall be a condition for authorization of monthly payments to <br />
The URL can be used to link to this page
Your browser does not support the video tag.