PROGRESS SCHEDULES <br />Section 01310 <br />15-1207 <br />actions (and any others he may deem necessary) at no additional cost to the Owner: <br />1. Increase construction manpower in such quantities and crafts as will substantially <br />eliminate the lag in schedule progress. <br />2. Increase the number of shifts per work day, work days per week, or amount of <br />construction equipment, or any combination of the foregoing, sufficient to substantially <br />eliminate the lag in scheduled progress. <br />3. Re -schedule activities to achieve maximum practical concurrency of accomplishment. <br />4. Those actions determined necessary to re-establish the original scheduled progress <br />shall be incorporated into the next schedule update. Should the results of the planned <br />corrective actions prove insufficient, additional corrective actions shall be taken. <br />5. The submission of an amended schedule will not relieve the Contractor of the <br />responsibility to notify the Architect in writing of all experienced or anticipated delays in <br />the prosecution of the work. <br />PART 2 - MATERIALS <br />Not Used <br />PART 3 - EXECUTION <br />Not Used <br />END OF SECTION <br />i.11207lincoln es - cafeteria replacementl4.06 projman101310—progress schedules.doc <br />Last Updated. 09/06/05 <br />3 <br />