• Ensure anchor points for winch or other lift device(such as davit arm)are engineered for intended use.
<br /> Geosyntec Procedure(s):HS-506-Cranes
<br /> FORKLIFT ❑In addition to general safety practices for heavy equipment(above),as applicable:
<br /> I Hazards:Struck-by,run-over, • qualified operator,per established forklift training(certificate is required).
<br /> overhead hazards,caught between • Equipment inspected daily and documented on Forklift Preoperational Inspection Checklist.
<br /> (pinch points),roll over,fluid leaks. • Do not exceed lifting load limits.
<br /> • Forklift shall not be moved/driven with empty forks in raised position.
<br /> • When not in use,forks lowered,brake set,controls in neutral,key removed.
<br /> • At no time may the operator leave the seat of the forklift when a load is suspended on or below the forks.
<br /> i
<br /> Geosyntec Procedure(s):HS-505-Safe Operation of Forklifts,HS-132-Competent Persons
<br /> AERIAL LIFTS i ❑See Section B.4.,"Fall Hazards"
<br /> Geosyntec Procedure(s):HS-509-Aerial Lifts
<br /> TRENCHING/EXCAVATION ❑Safe work practices when personnel will enter trenches/excavations:
<br /> Hazards:Cave-in,hazardous • Activities under supervision/oversight of competent person,daily inspection.
<br /> atmosphere,structures& Excavated materials placed at least 2'from trench sidewall.
<br /> foundations,falls into excavations . Prevent water accumulation in trench.
<br /> • Sloping&shoring for excavations>_20'must be approved by a professional engineer.
<br /> • Sloping/shoring/trench box for excavations>_5'when persons enter trench/excavation.
<br /> • Sloping/shoring/trench box for shallow(<5')excavations with cave-in hazard.
<br /> • Workers in trenches to be within 25 feet of ladder or sloped entryway.
<br /> • Excavations to be protected by perimeter fencing(not barricade tape),if potential for personnel to fall into.
<br /> • If potential for atmospheric hazard,see Section B.10,"Confined Space Entry,Hazardous Enclosed Spaces"
<br /> Geosyntec Procedure(s):HS-402-Excavation and Trenching,HS-132-Competent Persons
<br /> ❑ IMPORTANT! This work may/will ❑ Follow safe work practices per Section B.9.,"Utility Related Hazards"
<br /> include close proximity to overhead i
<br /> j and/or underground utility lines.
<br /> DEMOLITION ❑Develop/implement demolition safety plan.
<br /> Geosyntec Procedure(s): HS-132-Competent Persons
<br /> BLASTING ❑Develop/implement blasting safety plan.
<br /> Geosyntec Procedure(s):HS-307-Blasting and Use of Explosives,HS-132-Competent Persons
<br /> PUBLIC AT RISK,SITE SECURITY ❑ During site operations protect public(overhead protection,barriers,warning signs).
<br /> ❑ During off hours,protect public with barriers,warning signs/lights,other measures as appropriate.
<br /> ❑Lock/secure hazardous materials and/or equipment.
<br /> 6.8. ELECTRICAL HAZARDS ❑ Applicable ® Not Applicable,Not Anticipated
<br /> EXPLANATORY NOTES,CLARIFICATIONS: Electrically powered equipment may be used during the project,including electrical fans for use as engineering control(i.e.
<br /> vapor mitigation).
<br /> BASIC ELECTRICAL HAZARDS TO ❑ Follow safe work practices:
<br /> SKILLED NON ELECTRICAL WORKERS • Control water-related/wet-location hazards in a manner appropriate for the job tasks/equipment/tool.
<br /> Equipment/tool use/operation,use • Never touch electrical equipment if you are wet,or standing in water or on wet surfaces.
<br /> of extension cords,working near Use extension cords/power cords properly,prevent damage,take out of service if damaged.
<br /> electrical equipment. • Inspect tool/equipment/extension cords/power cords/welding cables before each use;do not use if damaged.
<br /> • Use GFCI-protected outlet or portable GFCI in wet locations,outdoors,basements,concrete floors.
<br /> Hazards:Electrical shock,secondary . Ensure live parts are guarded,enclosures secure.
<br /> hazards(falls,other injuries). • Enclosures,circuits properly labeled.
<br /> Geosyntec Procedure(s):HS-121-Electrical Safety
<br /> HANDS-ON ELECTRICAL WORK BY ❑ Implement electrical safe work practices pertaining to:
<br /> ELECTRICAL WORKER/TECHNICIAN: • Worker training/qualification(Level 1,Level 2,Level 3)
<br /> ❑Voltage<50 v • General electrical safe work practices,grounding,use of GFCIs
<br /> ❑Voltage 50-600v j • Safe work practices during diagnostics/troubleshooting,maintenance,repair
<br /> ❑Voltage>600v i • Safe design features for electrical equipment
<br /> ❑AC ❑DC ❑3-phase • Arc flash protection
<br /> ❑Battery and/or solar power
<br /> Geosyntec Procedure(s):HS-121-Electrical Safety,HS-119-High Voltage Electricity Safety
<br /> ❑Capacitor/transformer
<br /> LOCKOUT/TAGOUT OF ELECTRICAL 1 ❑ Implement control-of-hazardous-energy practices(lockout/tagout),provide lockout/tagout locks and
<br /> ENERGY devices,training workers,designate"authorized"personnel,notify"affected"personnel.
<br /> Geosyntec Procedure(s):HS-119-Lockout Tagout,HS-121-Electrical Safety
<br /> IMPORTANT! This work may/will ❑ Follow safe work practices per Section B.9.,"Utility Related Hazards"
<br /> include close proximity to electric
<br /> utility lines.
<br /> Geosyntec° THA—Drilling/Development Operations Safety 1/29/2019