Work Plan for Shallow Soil Assessment and Proposed Well Sampling Schedule Modification <br />Stockton Charter Way Commingled Plume #CP0057 <br />February 17, 2023 <br />3.0 OFFSITE WELL INSTALLATION <br />Per the CRWQCB-CVR letter dated December 20, 2022 (Appendix A),Stantec will coordinate <br />installation of deep offsite wells SMW-34D, SMW-34E, and SMW-36E at locations shown on <br />Figure 2. Wells will be installed per Stantec's February 2016 Work Plan at the following link for <br />reference: <br />https://documents.geotracker.waterboards.ca.gov/esi/uploads/geo report/3987128973/TO60770 <br />0702.PDF <br />Offsite well installations will require property owner coordination and request for permission to <br />access the property. Once access is secured, Stantec will obtain well installation permits from <br />SJCEHD. If possible, field work will be coordinated to occur along with the shallow ARCO soil <br />assessment and well destruction and repairs as discussed further in the following sections. <br />® Stantec 7 <br />