Laserfiche WebLink
San Joaquin County Environmental Health Department 5044.000.016 <br /> River Islands— Levee Relief Wells November 11, 2022 <br /> WORK PLAN FOR RELIEF WELL INSTALLTION Page 2 <br /> Filter Pack <br /> Based on the anticipated grain size of the soil within the proposed relief wells, #3 8x20 clean sand <br /> filter pack material will be placed in the annular space around the relief well screens to a minimum of <br /> 2 feet above the highest screen slot. The filter pack will be pumped as a water-filter pack slurry using <br /> a gravel pump. Tremie method will be used for placement of filter material to maintain a continuous <br /> flow and reduce segregation during placement. After the tremie pipe has been lowered to the bottom <br /> of the hole, filter pack material will be pumped as the tremie pipe is raised. The filter pack will extend <br /> about 2 feet above the top of the screen and the entire screen interval should be swabbed to help <br /> consolidate the filter pack material. <br /> Top Seal <br /> The top seal will consist of a bentonite layer above the filter pack and a sand-cement slurry.A layer of <br /> bentonite chips, at least 1 foot thick,will be placed on top of the filter pack material after consolidation. <br /> The bentonite should hydrate for at least 1 hour. Each well will be completed with a top seal of <br /> sand-cement slurry mixed in accordance with the California Well Standards: sand-cement shall be <br /> mixed at a ratio of not more than 188 pounds of sand to one 94-pound sack of Portland cement(2 parts <br /> sand to 1 part cement, by weight)and about 7 gallons of clean water,where Type I or Type II Portland <br /> cement is used.This is equivalent to a`10.3'sack mix.The sand-cement slurry will be pumped through <br /> a tremie pipe installed to 1 foot above the top of the bentonite seal. It may be practical to install a <br /> temporary 12-inch-diameter surface casing to a depth of approximately 12 feet prior to drilling the <br /> 10-inch bore and pour several top seals at one time using a ready-mix delivery truck. Depending on <br /> the final wellhead below-grade connections, it will be prudent to leave the top of the cement slurry <br /> about 3 feet below grade. After final wellhead below-grade grade connectors are in place, the <br /> remaining space will be filled with additional sand-cement slurry, as described above. <br /> The top of the well casing will be fitted with a check valve to prevent water from entering the well from <br /> the top. The valve will fit inside the well casing and sit flush on top of the casing with a gasket to <br /> prevent leakage. Based on our conversations with our client, we understand that a manhole or vault <br /> will be installed at each well. The vault size should accommodate routine future access to the well <br /> casing for inspection and maintenance, including well rehabilitation. <br /> See the Relief Well Details(Figure 3)for more information regarding well construction. <br /> SCHEDULE <br /> We plan to begin well construction beginning December 5, 2022, pending approval of this work plan <br /> and favorable weather. If you have any questions or comments regarding this letter, please call and <br /> we will be glad to discuss them with you. <br /> Sincerely, <br /> Q�pFESS/O <br /> ENGEO Incorporated ����` �,`IE HA"o <1c� <br /> No. 2804 <br /> /aso:ndore ZSteve Harris, GE �q TECHN��o��P <br /> OF C ALA <br /> js/sdh/ar <br /> Attachments: Figures 1 through 3 <br />