GENERAL NOTES <br />1. One week prior to the start of work, the Contractor shall furnish to <br />the Engineer a schedule showing proposed street closures on each <br />half—day basis. No work shall commence until this schedule is <br />approved by the Engineer. <br />2. All <br />intersection <br />radii <br />within <br />project limits <br />shall be slurry sealed to lip <br />of <br />existing curb <br />and <br />gutter <br />or edge of <br />pavement. <br />3. Before slurry seal is to be applied to any area, the Contractor shall <br />protect all utility covers, including but not limited to maintenance <br />holes, water valves and survey monument frames and covers. <br />Contractor shall remove protective covers after slurry seal. Full <br />compensation shall be considered as included in the unit price for <br />5 <br />[:1 <br />II <br />9. The Contractor shall not apply slurry seal coat on the stamped asphalt <br />crosswalk areas (Waterloo Road). All necessary precautions must be taken <br />by the Contractor to prevent any damage to the stamped asphalt <br />crosswalks. In the event that such damage should occur from the <br />Contractor's operations, the Contractor shall repair or replace or bring to <br />original condition the damaged stamped asphalt crosswalk at the <br />Contractor's expense. <br />w <br />Latex Modified Slurry Seal item of work. �d0 <br />Surface preparation work shall be as directed by the Engineer. <br />Locations and dimensions of pavement repair will be determined by -, �e� <br />the Engineer and shall be in place for 18 hours prior to placing 0 C' <br />slurry seal. <br />The Aggregate for Latex Modified Slurry Seal shall be Type II. �l fit <br />1> <br />The Contractor is to remove and dispose of all existing Thermoplastid, <br />Traffic Stripes and Pavement Markings in all areas. The cost for this.-; c <br />work is to be included in the contract price paid for Remove a� <br />Thermoplastic Traffic Stripes and Pavement Markings item of work anc y m <br />no separate payment will be made therefor. <br />Street sweeping will be performed routinely throughout the duration <br />of the slurry seal operations of the project per the specifications. <br />All streets to be slurry sealed will be swept immediately prior to the <br />application of the slurry seal coat. Twenty four (24) hours after the <br />application of the slurry seal coat, the areas will be swept again to <br />recover any loose aggregate from the area. Furthermore, sidewalks, <br />gutter pans/flow lines and streets will be cleaned and kept in order <br />throughout the duration of the project. Full compensation for these <br />sweeping operations shall be considered as included in the contract <br />unit price paid per square yard for Latex Modified Slurry Seal item <br />of work and no separate payment will be made therefor. <br />COUNTY OF SAN JOAGENERAL <br />QUIN <br />Areas in County right—of—way used by <br />8. The Contractor shall obtain an <br />Encroachment Permit from the City of <br />storage of materials <br />Stockton for traffic control signage <br />placed in the <br />City's <br />rights—of—way. <br />and/or storage of <br />Full compensation for obtaining <br />an Encroachment <br />Permit <br />from the City <br />condition to staging <br />shall be included in the various <br />contract items of <br />work <br />and no <br />f, <br />separate payment will be made <br />therefor. <br />property owner to <br />stage equipment or <br />store <br />materials on private <br />property. The Contractor shall provide <br />a letter <br />of release from the <br />Z <br />0 <br />of the areas utilized for staging <br />and/or storage of materials. <br />COUNTY OF SAN JOAGENERAL <br />QUIN <br />Areas in County right—of—way used by <br />the Contractor for <br />staging and/or <br />storage of materials <br />shall be approved <br />by the Engineer. The areas <br />utitilized by the Contractor <br />for staging <br />and/or storage of <br />materials <br />shall be restored to <br />their original condition. Any damages <br />or unclean <br />condition to staging <br />or storage areas <br />shall be repaired at <br />the Contractor's <br />own expense. It shall <br />be the Contractor's responsibility to <br />obtain <br />permission from the <br />property owner to <br />stage equipment or <br />store <br />materials on private <br />property. The Contractor shall provide <br />a letter <br />of release from the <br />property owner(s) <br />of the areas utilized for staging <br />and/or storage of materials. <br />The Contractor shall plane existing surface rut on the existing pavement <br />(See Planing Asphalt Concrete Pavement Detail on Sheet 8). All necessary <br />precautions must be taken by the Contractor to prevent any damage to <br />traffic loops. In the event that such damage should occur from the <br />Contractor's operations, the Contractor shall repair or replace or bring to <br />original condition the damaged traffic loop(s) at the Contractor's expense. <br />� Const <br />I <br />Limits of Clearing and Grubbing <br />EP I EP <br />Refer to tables on Sheets 9-10 <br />E I Latex Modified E <br />c Slurry Seal (Type II) <br />0 0 <br />r --- U U <br />SHOULDER DETAIL Existing Roadway SHOULDER DETAIL <br />with Curb & Gutter (Typ) without Curb & Gutter (Typ) <br />NO SCALE I NOTES & <br />TYPICAL SECTIONJI <br />DRAWN BY DATE PROJECT ENGINEER DATE CHECKED DATE <br />Juon Acevedo 0912 ��i�' � SO s X�7 iL/SeI <br />TYPICAL SECTION <br />SLURRY SEAL 2013 <br />(Road Districts 1, 2, and 4) <br />Sheet No. <br />7 of 11 <br />