Proposed Remedial Implementation Schedule - Former Chevron Station #9-5775, Lodi, CA <br />March 31, 2000 <br />plans to obtain a CalTrans encroachment permit to bring a water line onto the property from Kettleman <br />Lane, and has indicated that it would be best if the treatment system discharge and water lines were <br />installed at the same time. <br />• Soil vapor extraction pilot testing will begin on April 5, 2000. A portable vapor extraction system will <br />be used to extract soil vapors from the site on a weekly basis for up to 5 weeks. San Joaquin Valley <br />Unified Air Pollution Control District rules allow up to 5 calendar days of pilot testing without a final <br />discharge permit. Vapor extraction pilot testing is tentatively scheduled for April 5, 12, 19, 26, and May <br />3, 2000. Application for the final discharge permit will be made during the pilot testing period. <br />A search of Department of Water Resources (DWR) for wells within a %i mile of the site was conducted <br />on March 15, 1999 (GR report #346408.04-2, Monitoring Well Installation Report, dated June 2, 1999). <br />A door-to-door survey of properties within 500 feet of the site will be conducted to identify <br />undocumented wells in the vicinity. The well survey will be performed by June 1, 2000. <br />It will not be possible to meet the RWQCB's April 24, 2000, deadline for installation and continuous <br />operation of an interim groundwater pump and treat system. However, GR has already developed a <br />conceptual plan to install both soil vapor and groundwater extraction and treatment systems at this site. <br />Chevron and GR have met with Prime Shine to coordinate construction schedules and placement of the <br />treatment equipment, and Chevron has subleased space for the treatment compound. GR is currently working <br />with Westates Carbon to finalize the design of the groundwater treatment system. Plans for the construction <br />of the treatment system and compound have not been submitted to the City of Lodi for review and approval, <br />and we do not have a permit for discharge of the treated effluent. Based on these factors, we anticipate this <br />system will be operational by September 1, 2000. <br />If you have questions, please call us at 916.631.1300 if you have questions. <br />Sincerely, <br />Gettler-Ryan Inc. <br />Stephen J. Carter, R.G. <br />Senior Geologist <br />cc: Mr. Bob Cochran, Chevron Products Company, P.O. Box 6004, San Ramon, CA 94583 <br />Mr. Marty Hartzell, Regional Water Quality Control Board, 3443 Routier Road, Suite A, <br />Sacramento, CA 95827-3003 <br />Ivern and Roger Baffoni, 1175 Orangewood Drive, Lodi, CA 95240 <br />346408.07 <br />