Laserfiche WebLink
' 4 ESTIMATED SCHEDULE <br /> The estimated schedule for equipment specification, procurement, <br />' installation, and startup is in Figure 2 Equipment delivery schedules may <br /> vary at the time of order No time has been allocated for preparation of <br /> bid documents Construction schedules may vary depending on seasonal <br /> conditions Utility service connections and permit applications will also <br /> affect construction schedules <br /> Figure 2 <br /> ESTIMATED SCHEDULE <br /> ITEM WEEK <br /> NUMBER PROJECT TASKS 1 2 3 4 5 6 7 8 9 10 11 12 <br /> 1 System Specification <br /> 2 Equipment Procurement <br /> 3 Trailer Modification <br />' 4 Well/Piping Installation <br /> 5 Trailer Installation <br /> 6 System Startup <br /> Final Remediation Plan <br /> Prepared for Rmi%mo BAIQNG COMPANY 10 Prepared by Burlington Environmental Inc <br /> E 112138211259971TESTEVAL DOC 211/95 <br />