3 . Activities Next Quarter <br /> Groundwater levels will be measured in all wells . Sam- <br /> ples will be collected and analyzed according to the <br /> revised workplan. The attached table lists the wells <br /> to be sampled. Extraction Well A-9 may be replaced by <br /> converting DSW-6B to an extraction well. Assuming this <br /> is feasible, work may begin this quarter, using the <br /> resources saved by reducing the groundwater monitoring <br /> program. <br /> TASK 4--AQUIFER TESTING <br /> 1 . Progress made this quarter <br /> Analysis of the data from the pumping tests was com- <br /> pleted. Lateral hydraulic conductivity ranged from 14 <br /> to 49 feet per day (ft/d) , and the ratio of lateral to <br /> vertical hydraulic conductivity was determined to be <br /> approximately 3 :1 . <br /> A technical memorandum describing the pump test proce- <br /> dure , results , and data analysis has been prepared and <br /> submitted separately in August 1988 . <br /> 2 . Problems Identified <br /> None. <br /> 3 . Activities Next Quarter <br /> None . <br /> 4 . Schedule for Completion <br /> The scope of work defined in the workplan has been com- <br /> pleted. <br /> TASK 10--TANK INTEGRITY ASSESSMENT <br /> 1 . Progress Made this Quarter <br /> Agreement was reached on how to decommission the re- <br /> maining underground tank at the site. The empty <br /> creosote/oil unloading tank, no longer in use , is <br /> located in the plant site central process area. Soils <br /> in the process area are considered contaminated from <br /> the surface down to the groundwater. The shallow <br /> groundwater under the process area, including the <br /> creosote/oil tank, is contaminated from past practices. <br /> Well A-8 , located in the shallow groundwater near the <br /> tank, is being pumped to remediate groundwater con- <br /> tamination in the process area . Since the tank is <br />