Laserfiche WebLink
2. BALLAST <br />Place tanks in the hole, adding only enough ballast to <br />sink them. Ballast level in tanks must never exceed water <br />level in hole during installation. While adding ballast, only <br />use lifting cables to keep tanks in position. Tanks should <br />be free to roll slightly. The lifting cables and toglines <br />must be carefully tended. <br />Caution: Do not place tanks on timbers, beams or cradles <br />3. LEVEL TANKS <br />While leveling tanks, insure that minimum spacing between <br />tanks is maintained. When anchoring, place straps over <br />tanks and follow procedures in Section XIV -8. <br />4. BACKFILLING <br />Distribute backfill evenly around tanks and continue <br />procedures outlined for dry hole installation. <br />XIV -8 ANCHORING <br />Tanks must be anchored where high water tables exist, surface <br />water could flow into hole, or other water conditions could <br />exist in a dryhoe. All 4' & 70' tanks must be anchored <br />ed <br />without exception, regardless of groundwater conditions. <br />1. HOLD DOWN STRAPS <br />Use preformed hold—down straps furnished only by original <br />tank fabricator at designated strap locations marked on tanks. <br />Steel tank straps are furnished by tank fabricator with o <br />construction felt which MUST be placed between the straps <br />and the tank shell. Anchor straps must align with headman <br />anchor points +/— 1". Do not place straps or cable anywhere <br />else on tank shells. <br />Attach hold—down straps to anchor paints with 1/2" diameter <br />7 x 19 plow steel wire rope with blue steel center (no <br />fiber core) loops per D-97008 using three cable clamps and <br />heavy duty cable thimbles. All straps should be tightened <br />with turnbuckles to give a snug fit of strap to tank rib. <br />Turnbuckle diameter to be 1-1/4" hook type or 3/4" eye <br />type. 1" clevis—clevis turnbuckles may be used indigo of cables. <br />2. ANCHOR POINTS <br />Anchor points to be fabricated from round steel bar stock <br />of anchor bolt grade steel, formed as shown on drawing <br />D-97008. Use 1" diameter bar a 2—tank anchor and 3/4" <br />diameter bar for a 1—tank anchor. <br />3. DEADMAN ANCHORS <br />The weight of backfill above a deadmon on each side of a <br />tank to which they are anchored provides the additional <br />hold down force required to prevent float—out under the <br />hold—down force required to prevent float—out under the <br />most adverse conditions. Deadman may be fabricated in 2 <br />pieces placed end—to—end without gaps (minimum 2 straps <br />per deadman) where the total length is at least as long as <br />the tank itself. See D-97008 for details. <br />Deadmen should be Installed along the center line of <br />anchor points, taking care to have good cross alignment <br />+/— 1" with adjacent deadman anchors. The two outer anchor <br />points should be used for lowering deadmen into the tank <br />hole. If the contractor elects to cast deadmen in place <br />in the hole, the some anchors should be used with equal <br />reinforcement. <br />Any other substitute method <br />will require <br />equal horizontal <br />area, anchor <br />points of <br />equal <br />strength to <br />the wire rope <br />required, and <br />approval <br />of the <br />Shell engineer. <br />Diameter <br />4. CHANCE ANCHORS <br />Chance anchors will not be permitted under any <br />circumstances. <br />5. ALL ANCHOR METHODS (Minimums per anchor point) <br />TANK DIAMETER <br />XIV -9 SOIL STABILIZATION/FILTER FABRIC EXCAVATION LINER <br />Soil stabilization/filter fabric as specified below will be <br />used to line the bottom and side walls of all excavations for <br />ALL tanks except those in solid rock. For purposes of this <br />specification, solid rock will include igneous rocks (granite, <br />etc), sedimentary rocks (conglomerates, sandstone, shale, <br />limestone, etc), and metamorphic rocks (gnieses, schists, <br />etc). <br />If only a portion of the hole is excavated from solid rock, <br />then only that portion, which is not, should be lined. (For <br />instance: If only the bottom foot or so of the excavation Is <br />in solid rock, then the sidewalls should be draped with the <br />fabric so as to overlap into the rock area.) <br />There are several inexpensive inert soil stabilization filter <br />fabrics available which provide a separation between existing <br />soil and non—compatible backfills. When this material is used, <br />the 1/2 tank diameter spacing from ends and sides of tanks to <br />hole walls is not required. <br />Filter fabric is generally <br />6' <br />(or less) <br />8' <br />10' <br />Wire Rope (Recommend <br />1,000 yards <br />and in 12'-7" <br />and 15'-7" <br />7 x 19 plow steel) <br />be laid with <br />minimum laps <br />of <br />Diameter <br />3/8" <br />1/2" <br />1/2" <br />Tensile Strength <br />9000 <br />12500 <br />16000 <br />Turnbuckle Diameter <br />See D-97005 or 0-97009 for a <br />suggested layout method <br />of utilizing <br />Hook Type <br />3/4" <br />1-1/4" <br />1-1{4" <br />Eye Type <br />1 /2" <br />3/4" <br />1' <br />XIV -9 SOIL STABILIZATION/FILTER FABRIC EXCAVATION LINER <br />Soil stabilization/filter fabric as specified below will be <br />used to line the bottom and side walls of all excavations for <br />ALL tanks except those in solid rock. For purposes of this <br />specification, solid rock will include igneous rocks (granite, <br />etc), sedimentary rocks (conglomerates, sandstone, shale, <br />limestone, etc), and metamorphic rocks (gnieses, schists, <br />etc). <br />If only a portion of the hole is excavated from solid rock, <br />then only that portion, which is not, should be lined. (For <br />instance: If only the bottom foot or so of the excavation Is <br />in solid rock, then the sidewalls should be draped with the <br />fabric so as to overlap into the rock area.) <br />There are several inexpensive inert soil stabilization filter <br />fabrics available which provide a separation between existing <br />soil and non—compatible backfills. When this material is used, <br />the 1/2 tank diameter spacing from ends and sides of tanks to <br />hole walls is not required. <br />Filter fabric is generally <br />spunbonded <br />polypropylene <br />available in <br />rolls of 100, 300, and <br />1,000 yards <br />and in 12'-7" <br />and 15'-7" <br />widths. Material should <br />be laid with <br />minimum laps <br />of <br />approximately 18" width <br />so that the <br />excavation is <br />completely <br />lined and overlaying the <br />top of the <br />hole perimeter <br />one to two <br />feet and pinned in place. <br />See D-97005 or 0-97009 for a <br />suggested layout method <br />of utilizing <br />15'-7" wide <br />material. <br />Acceptable fabrics by brand name: <br />Du Pont "Typor' Style 3401 — 4 oz/s.y. <br />Monsanto "Bidim" C-22 — 4 oz/s.y. <br />Phillips Supoc' Fabric — 4.1 oz/s.y. <br />Celanese "Mirafi" 140 Fabric — 4.1 oz/s.y. <br />CONCRETE SLAB ALTERNATE <br />In situations involving extremely low bearing soil and adverse <br />water conditions, a concrete slab under the tanks may be used <br />as on alternate to the filter fabric method. Install <br />prefabricated reinforced concrete deadmen as outlined in <br />Section XIV -8. Between the deadmen, under each tank area, <br />construct a reinforced concrete slab with a minimum thickness <br />of 6" reinforced with 6" x 6", 6/6 wire mesh. <br />If contractor elects to cast a single slab, including the tank <br />anchors, the slab should be deepened to provide the some cross <br />section area as provided by the deadmen, and install the some <br />steel reinforcement and anchor points. <br />If a concrete slab is used under the tanks, the filter fabric <br />should be used as well to line the walls of the excavated area. <br />XIV -10 BALLASTING <br />When ballasting of fiberglass tanks is required, water or <br />product may be used and ballasting done in strict compliance <br />with these specifications. Prior to delivery of Shell gasoline, <br />the following items should be taken into consideration by the <br />contractor: <br />Forty—eight hours notice to plant is required for delivery of <br />product for ballast. Assure proper access to site for delivery <br />vehicle and advise Shell engineer of hose length requirements <br />needed to make delivery. <br />A Shell representative must be on hand to verify and accept <br />delivery and custody of product for the district. Upon <br />completion of delivery, contractor and Shell representative <br />should jointly verify the quantity of product delivered. At <br />this time, suitable locks will be provided by Shell to secure <br />fill caps. <br />XIV -11 CHECK TANK DIAMETER FOR PROPER INSTALLATION <br />FLAY IT SAFE — CHECK VERTICAL DIAMETER DEFLECTIONS <br />THROUGHOUT THE ENTIRE INSTALLATION PROCESS <br />Normal installation with specification pea gravel, and tank <br />properly bedded, will generally result in a decrease in the <br />vertical diameter of on 8' diameter tank of approximately <br />1% (1") at the tank mid—length for fiberglass tanks and <br />roughly 1/2% (1/2") for jacketed steel tanks at the some <br />poind. While slightly larger deflections are within the design <br />tolenonce, the above deflection limits should be considered to <br />be the maximum acceptable without involvement of the tank <br />manufacturer's technical staff. Should deflections exceed <br />these limits, it's an indication of improper backfill/compaction <br />and it may be necessary to remove and reinstall the tanks. <br />The peogrovel may contain excessive fines below specification <br />and some mechanical compaction by vibration may be <br />required for proper consolidation of the backfill material. <br />XIV -12 FLOAT OUT <br />Tanks not anchored (with backfill to top of tanks ready for <br />piping and fully ballasted with gasoline) con float out should <br />the tank hole become substantially flooded with surface/ground <br />water. Anchored tanks, fully ballasted, and backfilled <br />similarly will not float out due to the weight of backfill on <br />tank slab or deadmen. <br />In either case, it is therefore essential that the tank hole <br />be filled completely with backfill to top of tanks. If not <br />anchored, a minimum of 24" of additional fill above tanks would <br />be required to prevent floatation under extreme conditions. <br />Thus, it's most important that necessary installation and piping <br />above the tanks be completed as quickly as possible so that this <br />additional fill con be placed. <br />XIV -13 TANK TOP PIPING <br />1. INTERNAL PIPING OR SUBMERGED PUMP <br />It is recommended that actual clearances from the top of <br />the tank (pipe connection fittings) to the tank bottom be <br />measured to insure that adequate clearances are maintained <br />for submerged pump, fill tube, or any other internal piping <br />installed. <br />The pump and attached piping must be free to move with the <br />tank. Use fill box around fill pipe at grade where <br />asphalt or concrete pad is used. Do not place brick or <br />other spacing material on top of tanks. <br />XIV -14 FILLINJG TANKS <br />Do not fill tanks until backfill is to top of tank. Never add <br />product or water for hold down in dry hole conditions until <br />backfilling Is completed. <br />EXCEPTION: See Installation Procedure — Wet Hole <br />15 ADDINJG TANKS TO EXISTING INSTALLATIONS <br />Tanks can be added to existing installations. It is important <br />to always remember that all tanks require good foundation <br />support from surrounding soil and are not self—supporting under <br />fuel or overburden loads. The following guides are suggestions <br />to reduce loads from soil or product on uncovered tanks so no <br />damage will occur. Final selection of an installation method is <br />the responsibility of the Shell engineer depending on local site <br />conditions. See plot plan and addenda, <br />ISOLATED BURY (PREFERRED) <br />Install tanks in a separate hole that is a minimum of 5' <br />from edge of original tank installation hole. It is <br />critical that undisturbed soil between the new excavation <br />and the original hole be maintained. Keep surface loads off <br />existing tanks. <br />2. BURY IN SAME HOLE (ALTERNATE) <br />A. <br />Lower product level in existing tanks to less than <br />1/3 tank capacity, <br />B. <br />Remove surface pod, if one exists, to reduce overburden <br />loads and backfill levels. <br />C. <br />Excavate for new tanks, leaving as much backfill as <br />possible around existing tanks. <br />D. <br />During installation, existing tanks must not be <br />Pipe Length/Degree of Bend (Ft) <br />allowed to move, Shoring and sheeting may be <br />1' <br />required to retain backfill_ <br />E. <br />Install new tanks as described earlier in these <br />instructions, leaving a minimum of 24" between new <br />22-1/2' <br />tanks and existing tanks. <br />F. <br />If backfill material other than pea grovel, stone, or <br />grovel crushings was used for existing tanks, an inert <br />filter fabric should be installed between ofd and new <br />MIN. <br />backfill to prevent any migration into new granular <br />MAX. <br />backfill which could lead to tank failure. <br />XIV -16 PERMANENT PIPE SUMPS <br />At the discretion of the Shell engineer, tank hole observation <br />sumps may be installed per Shell Installation drawings. These <br />Pipe sumps will consists of three (3) 4" slotted PVC pipes and <br />one (1) 8" slotted PVC pipe. Specifications for the pipe sumps <br />are indicated on the installation drawings. Sumps should be placed <br />in the tank hole before any pea gravel is installed so that the <br />bottom is resting on the filter fabric excavation liner. The <br />sumps and a water pump can very effectively be used to control <br />any water entering the hole during construction. <br />The Shell engineer can furnish a list of national suppliers <br />for machine slotted (.020") pipe. Solid PVC pipe can also be <br />purchased locally and perforated either in the contractor's shop <br />or at the job site. <br />Perforated pipe should be wrapped with filter fabric or double <br />wrapped with common hardware screen. Filter fabric is the <br />preferred wrapping, if available in smaller quantities. <br />All pipe joints MUST be threaded or slip—fit. NO GLUED JOINTS, <br />XIV -17 INSTALLATION INSPECTION PROCEDURE AND CHECKLIST <br />A completed "Installation Inspection Procedure and Checklist" <br />form is to be provided to the Shell Engineer for approval on <br />completion of the tank installation. FAILURE TO PROVIDE AN <br />ACCEPTABLY COMPLETED FORM WILL RESULT IN NON—PAYMENT OF THE <br />INSTALLER'S FINAL INVOICE. <br />XIV -18 TANK REPAIRS AND ADDITIONAL FEATURES <br />Tank repairs or the installation of additional tank features (turbine <br />sump collars, additional bungs, etc) may ONLY be accomplished by <br />factory trained and factory authorized personnel in order to maintain <br />the original testing laboratory listing. Such work by non—authorized <br />contractors or their personnel is STRICTLY FORBIDDEN. <br />XV — GASOLINE PIPING SPECIFICATIONS <br />XV -1 GENERAL <br />The contractor accepts full responsibility for proper handling <br />and installation of ALL primary and secondary piping and shall <br />insure that good workmanship practices and construction <br />procedures are followed throughout the installation, regardless <br />of the inclusion or omission of any applicable suggestion in <br />these instructions or on the drawings. <br />Unknown situations or conditions not covered herein are the <br />responsibility of the contractor. Manufacturer's specialists <br />and Shell engineers are available for consultation. The <br />presence of a Shell or Manufacturer's representative at an <br />installation site does not relieve the contractor of the <br />responsibility for a proper installation. <br />The contractor shall be responsible for proper safeguarding of <br />the installation and materials and equipment stored on the site <br />to prevent theft, vandalism or damage. <br />XV -2 SCOPE OF WORK <br />The piping system to be installed under this section will <br />include product, vent, and applicable vapor piping as shown on <br />the plot plan or covered in the addenda to these specifications <br />or on the related piping drawings. Included are appropriate <br />connections and appurtenances to the installed equipment in the <br />complete system, e.g., underground tanks, pumps, dispensers and <br />indicated vapor control or recovery equipment. Contractor <br />should refer to the plot pion for the orientation of connections <br />at tanks and pipe chases for piping. <br />XV -3 PIPING MATERIALS <br />1. All primary piping is to be alcohol—compatible Underwriters <br />Laboratory, Inc. approved reinforced thermosetting resin <br />Pipe (fiberglass), molded fittings and adapters. Refer to <br />the Approved Material List for current approved suppliers <br />and type of system to be used. <br />We anticipate adding specifications herein for contained <br />flexible piping after first resolving inadequacies in current <br />codes. Until further notice, Shell engineers may elect to <br />use contained flexible piping only on a site—by—site basis <br />with prior approvals of Marketing Engineering. Piping plans <br />for such projects must be prepared and approved by <br />Marketing Engineering. Shell field Personnel and consultants <br />are hereby Prohibited from wring such plans. <br />ALL SECONDARY CONTAINMENT PIPING HARDWARE MUST <br />ALLOW FULL EXPOSURE AND ACCESS TO ENTIRE PRIMARY <br />SYSTEM SURFACE, NOT JUST THE JOINTS AND FITTINGS. <br />Only "w t" primary piping (that routinely containing fuel such <br />os product lines) are intended to be secondarily contained. <br />"Dry" piping (vapor recovery, vents, etc) is intended to be <br />uncontained since these lines are not intended to carry <br />liquid at any time, are designed to prevent the intrusion of <br />liquids from the tank, and are sloped back to the tank to <br />prevent the retention of standing liquids. See appropriate <br />Installation drawings for details. Where mandated by local <br />codes, these lines can also be secondarily contained. <br />For Non—Alcohol Fuels <br />Fill pipes and other vertical risers at tanks and above <br />ground vent risers shall be standard galvanized steel <br />pipe with fittings standard galvanized malleable iron. <br />Galvanized malleable iron unions, where called for on the <br />detailed drawings shall be ground joint construction with <br />brass/brass seat, 150# for above ground and 250/300# for <br />below ground applications. Galvanized malleable iron <br />couplings, where required are to be extra heavy duty. <br />Joints of steel piping shall be made up with an approved <br />gasoline and alcohol pipe compound (no teflon tape). <br />For Alcoh Fuels an Blends: <br />here fuel contain r are likel, to contain alX.,eon <br />go vaniz pipe, o well as o r material may <br />used. Consult ith Ni Engineeri for uth e install9ons or up ode S. � <br />Flexible onnectors, here cane for, shall e U.L. <br />a r ed withit 3 oX swiveling d fitting. ee sect <br />All pipe,tangs, app enances, op tubes 3/76" <br />press equolizoti ( n boxes <br />valves JzFe to be fished <br />XV -4 PIPING INSTALLATIONS <br />1. PRIMARY PIPE SYSTEMS <br />Storage and handling, stringing, joining, layout and <br />preparation for installation, cutting, tapering, bonding, <br />curing, adaptors to steel piping, and flexible connectors <br />shall be in accordance with manufacturer's instructions or <br />recommendations. Contractor must be familiar with such <br />practices and procedures and follow some unless certain <br />instructions which are specificoliv covered in these <br />specifications, i.e., pipe burial, seem to be at variance. <br />In such case, Shell's specification will be followed. <br />All unconnected pipe stubs or runs shall be protected <br />during construction against the intrusion of dirt or other <br />foreign material into the piping system. Protective caps <br />used in shipping the pipe are suitable if taped in place. <br />Where repairs are found to be required during construction <br />or after testing or inspection, the defective portion of <br />the piping shall be removed and replaced with appropriate <br />new pipe and fittings. Repairs such as a sleeve type line <br />patch over a damaged pipe or a glass cloth and adhesive <br />build—up over a joint or fitting are not acceptable on new <br />work. <br />Based on criteria available from manufacturers we have <br />selected the following minimum bending radii for 2" to 4" <br />fiberglass pipe, which will simplify any field calculation <br />for installation of ❑ bend if one is required. <br />PIPF nIAMFfFR <br />Galvanized steel piping has been selected to be used in <br />conjunction or in lieu of fiberglass piping at such <br />locations where size of the piping, complexity of the <br />arrangement, structural needs, or aboveground application <br />precludes the use of fiberglass material. In such cases, <br />protection from galvanic corrosion may be required. All steel <br />piping joints shall be made up using an approved gasoline <br />and alcohol compatible pipe compound (no teflon tape). The <br />preferred thread compound for steel hardware is Gasiola Soft—Set <br />with Teflon as made by Federal Process Company, Cleveland, <br />Ohio 44122. Litharge and glycerine are not approved. All <br />unconnected pipe stubs, risers, or runs shall be capped to <br />prevent tampering or the intrusion of dirt. The use of a filler <br />material, such as plumber's string, in making a pipe joint when <br />threads are improperly cut is unacceptable. <br />These drawings and specificotions are Shell Oil Company's <br />(generic depictions of one or more components of its <br />standard retail service station designs. They are not <br />intended for use on specific projects. These drawings and <br />specifications are the confidential and proprietary property <br />of Shell Oil Company and shall not be copied or reproduced <br />without Shell's written authorization. <br />Shell Oil Company. All Rights Reserved 1997 <br />2" <br />Minimum Bending Radius (Ft) <br />57' <br />84' <br />108' <br />Pipe Length/Degree of Bend (Ft) <br />1' <br />1-1/2' <br />2' <br />(Example -15 degree bend—Pipe Length <br />15' <br />22-1/2' <br />30' <br />MIN. <br />LENGTH <br />MAX. <br />PIPE SIZE <br />BENDING RADIUS <br />OF PIPE <br />DEFLECTION <br />2 <br />57' <br />15' <br />24" <br />3" <br />84' <br />15' <br />16.2" <br />4�' <br />108' <br />15' <br />12.6" <br />Galvanized steel piping has been selected to be used in <br />conjunction or in lieu of fiberglass piping at such <br />locations where size of the piping, complexity of the <br />arrangement, structural needs, or aboveground application <br />precludes the use of fiberglass material. In such cases, <br />protection from galvanic corrosion may be required. All steel <br />piping joints shall be made up using an approved gasoline <br />and alcohol compatible pipe compound (no teflon tape). The <br />preferred thread compound for steel hardware is Gasiola Soft—Set <br />with Teflon as made by Federal Process Company, Cleveland, <br />Ohio 44122. Litharge and glycerine are not approved. All <br />unconnected pipe stubs, risers, or runs shall be capped to <br />prevent tampering or the intrusion of dirt. The use of a filler <br />material, such as plumber's string, in making a pipe joint when <br />threads are improperly cut is unacceptable. <br />These drawings and specificotions are Shell Oil Company's <br />(generic depictions of one or more components of its <br />standard retail service station designs. They are not <br />intended for use on specific projects. These drawings and <br />specifications are the confidential and proprietary property <br />of Shell Oil Company and shall not be copied or reproduced <br />without Shell's written authorization. <br />Shell Oil Company. All Rights Reserved 1997 <br />