Schedule Name: MARLEY COOLING TOWER COMPANY <br /> Project Manager: D.Y. BATES <br /> As of date: 3-Feb-87 9:32am Schedule File: B:SCHEDULE <br /> - OVERALL SCHEDULE FOR CLEAN UP AT STOCKTON PLANT(REVISED FEB 2.1987) <br /> 87 88 <br /> Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug <br /> Who Status 2 2 1 1 1 1 3 1. 1 2 1 4 1 1 1 2 1 1 1 <br /> MAR +++++++++♦ ... . <br /> IGENERAL CONSTRUCTION +++++++++++ <br /> ]PILOT TEST PROG DEVELOPMENT D MI <br /> ]PILOT TEST PROORAM D M. <br /> 1EQUIPMENT REDESIGN +•+++• - _-- <br /> lE%CHANGER INSTALLATION <br /> ]SECONDARY CONTAINMENT REVIEW D M <br /> (TANK CONSTRUCTION C ++++++++++++ . <br /> IEFFLUENT FORCE MAIN CONSTRUCT +++++++++. • - ---— <br /> (RECOVERY TANK DESIGN REVISION +++ <br /> 1RECOVERY TANK CONSTRUCTION <br /> ISTARTUP TREATMENT PLANT >M ' <br /> (OPERATIONAL TEST ==_ <br /> (TREATMENT PLANT N REVIIONRL :---.---•--- M== - <br /> I2PONDTREA CLOSURE PLAN REVIEW-A *+ <br /> 2POND CLOSURE PLAN REVISIONS <br /> 2POND CLOSURE PLAN REVIEW-B _--------- <br /> 2POND LIQUID REMOVAL <br /> 2POND BOTTOM SAMPLING <br /> 2POND STABILIZATION CONTRACT <br /> 2POND STABILIZATION •_____________ -- " <br /> 2POND EARTHWORK AND PAVING DOC --------- <br /> 2POND FILLING _______ <br /> 2CAP INSTALLATION <br /> 2PUMP STATION MODIFICATION '`--_---- ' <br /> 2PERIMETER DRAIN INSTALLATION <br /> 2DRAINAGE CONTROL CONSTRUCTION <br /> 2CERTIFICATION INSPECTION 1 ___- <br /> 2PONO CLOSURE COMPLETE M---------------- <br /> 3NPDES PERMIT MODIFICATIONS +++ ' <br /> 3NPDES PERMIT REVIEW AND APPRO "----'----"'------------------------------ <br /> 3PHASE III WELL INSTALLATION D MI <br /> 3PHASE III REPORT PREPARATION ++++++* " - <br /> 3PHASE III REPORT REVIEW ._______ ' <br /> 3EXTRACTION WELL INSTALLATION <br /> 3GROUND WATER FORCE MAIN DESIG <br /> 3GROUND WATER FORCE MAIN INSTN -- <br /> 3GROUND WATER SHAKEDOWN - <br /> 3GROUND WATER OPERATION COMMEN t •M--------------------------- . <br /> 4WORK PLAN UPDATE 0 M <br /> • 4WORK PLAN APPROVAL C +++++r++♦r____ <br /> 4SOUTH YARD SAMPLING C <br /> 4SOILS ASSESSMENT REPORT PREP C <br /> 450ILS ASSESSMENT REPORT REV IE C <br /> 4ASSESS. PROGRAM REPORTS APPRO C M <br /> 4FINAL MITIGATION PLAN PREPAR C <br /> 4MITIGATION PLAN REVIEW C _____________• <br /> 4MITIGATION PLAN APPROVED M------------ <br /> 4MITIGATION PLAN IMPLEMENTATIO C <br /> _______________________________________________________________________________________________________________________________ <br /> D Done === Task - Slack time (==---). or <br /> C Critical +++ Started task Resource delay - - <br /> R Resource conflict M Milestone > Conflict <br /> p Partial dependency <br /> Scale: Each character equals I week <br /> _______________________________________________________________________________________________________________________________ _ _ . .. . <br /> TIME LINE Gantt Chart Report _ Strip I <br />