Project Schedule <br /> Phase III <br /> Stockton Former MGP Site <br /> Receive PUC authority 12/17/93 <br /> Start Phase IIIc fieldwork 2 Wks after PUC authority received <br /> • Complete Phase IIIc fieldwork12/31/93 <br /> 2 Wks from start date <br /> Phase IIIb - Meeting with DTSC 1/14/94 <br /> 6 Wks after completing Phase 111a 3/11/94 <br /> Start Phase IIIc fieldwork 4 Wks after r n, <br /> receiving 6/20/94 <br /> offsite a&`,' "a ei <br /> F. 82e #a Well <br /> w, <br /> nstallatton µ" <br /> Complete Phase IIIc fieldwork 6 Wks after Phase IIIc start date <br /> 8/1/94 <br /> 6 Wks after receipt of Phase IIIc lab results <br /> Submit Technical Memorandum (approximately 10 Wks after completion of 10/10/94 <br /> Phase IIIc field work) <br /> Agency meeting to discuss TM and FS 2 Wks after submittal of TM <br /> PG&E response to TM comments 10/249 4 <br /> • 2 Wks after Agency meeting 11/7/94 <br /> * This date is an estimate and could be subject to change. <br />