James L. Tjosvold, P.E. <br /> January 24, 1997 <br /> Page 4 <br /> III. Schedule Changes: <br /> On August 21, 1996, PG&E submitted a revised project schedule which included action items <br /> and agreements reached during the August 8, 1996 meeting. This schedule included <br /> conducting additional soil borings in Area I, soil borings in Area II and the installation of an <br /> additional Zone B groundwater monitoring well. <br /> The August 21, 1996 schedule has been revised to allow for incorporation of the December, <br /> 1996 soil and groundwater investigation into the VLEACH model and into the FS. This <br /> revised schedule was submitted to the agencies on January 22, 1997. <br /> IV. Activities Planned for Next Quarter: <br /> The soil analytical results from the December, 1996 field work will be incorporated into the <br /> VLEACH model (creating new polygons). Additional sensitivity analysis will be performed <br /> on the VLEACH and groundwater mixing cell models in preparation for discussions on the <br /> final input parameters to be used in the VLEACH and groundwater mixing cell models (these <br /> models will be used to help evaluate remedial alternatives in the FS). A conference call and a <br /> meeting are planned to discuss the results of the December, 1996 soil and groundwater <br /> investigation and to discuss the results of the VLEACH model which is being revised to <br /> incorporate new soil data from the December, 1996 investigation. <br /> Future meetings to discuss and agree on the groundwater mixing cell model; the soil volume <br /> to be remediated; the remedial alternatives which will be screened in the FS; and the remedial <br /> alternatives which will be carried forward for detailed evaluation in the FS are also planned. <br /> The next quarterly groundwater monitoring will be conducted in March, 1997. <br /> V. Results of Analyses. Tests or Other Data: <br /> Groundwater sampling was conducted in December, 1996 and the analytical results will be <br /> submitted to DTSC and the RWQCB by January 31, 1997 in the "Quarterly Monitoring <br /> Report, PG&E Stockton Former MGP Site, Fourth Quarter, 1996". <br /> If you have any questions or require additional information, please call me at (415) 973-6254. <br /> Sincerely, <br /> Patricia Sullivan <br /> Project Manager Stockton Manufactured Gas Plant Site <br />