James L. Tjosvold, P.E. <br /> January 24, 1997 <br /> Page 3 <br /> II. Activities Performed During Current Quarter: <br /> On October 10, 1996, PG&E submitted its"Workplan for Additional Soil and Groundwater <br /> Investigation during the Feasibility Study" to DTSC and the RWQCB. This Workplan <br /> included additional soil borings in Area I; conducting DI WET and TCLP analyses on selected <br /> soil samples from Area I; the drilling of soil borings in Area II; and the installation of a Zone B <br /> groundwater monitoring well(s) at the perimeter of Area H. A final Workplan, revised to <br /> reflect comments received during an October 30, 1996 conference call between PG&E, DTSC <br /> and the RWQCB, was submitted to the agencies on November 13, 1996. This final Workplan <br /> was approved by DTSC on November 15, 1996. <br /> The field work for the additional soil and groundwater investigation approved by DTSC in <br /> November, 1996 took place between December 9, 1996 and December 20, 1996. Activities <br /> included: 1) drilling six soil borings in Area I to further define Source Areas 2 and 4, including <br /> the drilling of two additional borings beyond the four planned borings (these additional <br /> borings were determined to be needed based upon field observations) and drilling one soil <br /> boring to collect a sample from Source Area 2 for DI WET and TCLP analyses; 2) the <br /> installation of six soil borings in Area II, including three borings within the footprint of the <br /> former auto repair facility, two borings around a previous boring (MW-22R)which contained <br /> hydrocarbons in the groundwater and one boring outside the substation yard upgradient of <br /> Area II; and 3) the installation of a B Zone well along El Dorado Street (MW-26). Based <br /> upon field observations in Area II, it was determined that additional A and B zone wells were <br /> not needed. <br /> Soil borings were analyzed for PNAs, TPH-diesel, TPH-gasoline and BTEX(Area II soils <br /> were also analyzed for chlorinated solvents). In addition, three soil samples from Area I (one <br /> from Source Area 2 and two outside the source areas)were analyzed by DI WET for PNAs <br /> and TPH-diesel and by TCLP for TPH-gasoline and BTEX. Hydropunch samples were taken <br /> from the A Zone and the B Zone during the drilling of the new B Zone well (MW-26) and a <br /> groundwater sample was taken from the newly installed B Zone well (MW-26). These <br /> samples were analyzed for PNAs, TPH-diesel, TPH-gasoline and BTEX. The analytical <br /> results of this soil and groundwater investigation will be sent to the agencies prior to a <br /> conference call scheduled for February 13, 1997 to discuss the results of this soil and <br /> groundwater investigation. <br /> Quarterly groundwater monitoring was conducted in December, 1996. The results of this <br /> groundwater monitoring will be submitted to the agencies by January 31, 1997 in the <br /> "Quarterly Monitoring Report, PG&E Stockton Former MGP Site, Fourth Quarter 1996". <br />