Tentative Field Implementation Schedule for Installation and Operation of <br /> the AS/SVE Treatment System at The Transmission Shop Site in Stockton, CA <br /> Duration <br /> Key Activity Description <br /> Early Start Early End <br /> Equipment, material, and resource procurement 11/2/2009 4/26/2010 <br /> Permitting(air emissions,well installation, and electrical/gas connection) 11/2/2009 5/1/2010 <br /> Site preparation and initial setup(including utility clearance) 12/1/2009 12/11/2009 <br /> System construction (well drilling,piping,electrical oo up, and equipment installation, <br /> 12/14/2009 5/3/2010 <br /> System testing and startup/shakedown 5/3/2010 5/17/2010 <br /> Routine system operation and monitoring(including quarterly and semiannually 5/17/2010 5/16/2013 <br /> groundwater well sampling); <br /> System shutdown with one-year quarterly monitoring TBD TBD <br /> System decommissioning TBD TBD <br /> Note: <br /> Early start of the project is contingent upon receipt of notice to proceed from the client. <br /> A 6-month period is assumed for the electrical and possibly natural gas connections,from permit application <br /> to,final hookup. This time period is considered maximum but also typical based on other project experience <br /> involving PG&E. The actual time required may, however, be less but remains contingent upon PG&E's <br /> schedule after receipt of the permit application. <br /> System treatment period is assumed 3 years at a minimum <br /> TBD- To be determined later based on treatment progress results. <br />