fittings for later connection to the air injection piping and the air compressor. Fittings will also <br />be made to the existing monitoring wellheads for later connection to monitoring instruments, <br />including downhole probes and wellhead vapor detectors. <br />All drilling equipment will be decontaminated prior to and after use. Drilling equipment will be <br />decontaminated by steam cleaning. Non -disposable sampling equipment will be decontaminated <br />by the following procedure: wash with a mixture of non -phosphate soap (e.g., Alconox"') in tap <br />water, rinse with tap water, and then rinse with deionized water. <br />Because the well will be used for air injection as a biosparge well, no well development will be <br />performed following installation. <br />5.3 Groundwater Sampling <br />Groundwater samples will be collected from wells MW-4RS, MW -7S, and VW -21) for the <br />inorganic and nutrient analyses prior to biosparge testing. Groundwater samples will be <br />collected with the use of a low -flow pump with a flow-through cell. Water level and water <br />quality parameters (temperature, pH, conductivity, turbidity, dissolved oxygen, and oxygen - <br />reduction potential (ORP) will be measured in each well throughout purging. Depth to water, <br />date and time will be noted for each monitoring location. Sample collection will begin when <br />successive purge measurements meet the following criteria: <br />• pH +/- 0.1 pH unit; <br />• Temperature +/- 1 degree Fahrenheit; <br />• Conductivity +/- 5%; and <br />• DO +/- 10%. <br />Samples will be collected directly into laboratory -prepared containers, then capped, labeled and <br />placed on ice in an insulated ice chest. The samples will then be transported under chain -of - <br />custody manifest to a California -certified analytical laboratory via overnight courier. <br />5.4 Equipment Installation <br />The air injection system will consist of a portable, tank -mounted air compressor unit and rigid <br />' galvanized steel piping. No equipment pad will be required for the air compressor unit. Either <br />an onsite electrical supply or a generator will be used to power the compressor. The steel pipe <br />will be installed aboveground and connect the air compressor to the sparge well. Instruments, <br />such as pressure gauge and flow meter, and valves will be installed on the piping. Additional <br />monitoring ports will be installed on the piping as well as at the other observation wells. <br />I <br />Biosparge Pilot Test Final doc 5-2 Shaw Environmental, Inc. <br />