i <br /> Irk <br /> ' Site Background Information Former Stockton Plating Facility <br /> +, Page 6 of 7 <br /> GROUND WATER EXTRACTION SYSTEM INSTALLATION <br /> IFour`l 5-inch diameter, stainless steel QED Environmental model H23SET pneumatic powered, <br /> down-well pumps were installed in vapor extraction wells VW-1, VW-2, VW-3 and VW-4 The <br /> pumps were internally equipped with a one-way check valve to preverit back-flow The pumps°were ' ` " '`' M h <br /> installed in each well at a depth of approximately 45 feet bsg One-half inch diameter poly-vinyl <br /> chloride (PVC) tubing was routed from each pump to the top of each well casing and through a 2- ` <br /> inch diameter sanitary well seal In the remediation area, a manifold was created with independent I <br /> flow meters and a dedicated sampling port to allow sampling of each well independently without _ <br /> having to remove each respective well head assembly <br /> On 02 February 2004, a 4-inch diameter, stainless steel model 5S8 Grundfos Rediflow down-well <br /> ' pump equipped with 230 volt%2-horsepower 3-wire motors were installed in ground water extraction' <br /> I well EW-1 The Grundfos pump was installed in well EW-1 at a depth of approximately 65 feet » ' <br /> mbelow surface grade (bsg) Schedule 40, I-inch diameter PVC tubing was routed from the pump to <br /> the top of the well casing and through a 4-inch diameter sanitary well seal In the remediation area, <br /> Ii an independent flow meter and a sampling port was installed to allow sampling of the well without <br /> having to remove the well head assembly <br /> I 1 , <br /> Installation of Ground Water Treatment System <br /> I <br /> Threer I <br /> 2,000-gallon granular active carbon(GAC)media vessels, one 300'gallon poly tank(holding <br /> tank), one process pump and one sediment filter chamber were installed for the ground water <br /> I treatment system c t <br /> ,r r• k'. r <br /> Ground'water pumped from the recovery wells is initially routed-via the piping system to the 300- <br /> gallon poly tank(holding tank)prior to processing The holding tank is equipped with various water <br /> level'float controls to control the rate at which extracted water is introduced into the treatment <br /> vessels, to allow coarser sediment to settle out.prior to treatment and to provide safety shutoff <br /> a N <br /> I capabilities A high float (high-high)was installed near the top of the holding tank and is designed <br /> to shut,the entire system down if water level exceeds the high-high float A middle float (high- <br /> ' low)was'installed near the middle of the holding tank and is designed to turn on the process pump <br /> I when water level exceeds the high-low float A low float was installed near the bottom of the holding <br /> tank (low-low) and is designed to turn off the process pump <br /> A !/2-horsepower, single-phase centrifugal process pump was installed inside the holding tank The <br /> process pump is designed to process groundwater through the treatment system at a maximum flow <br /> rate of 10 gallons per minute (GPM) 3 7 <br /> . An electrical control panel was installed adjacent the process tank and pump Electrical wiring from I <br /> 5 <br /> Advanced GeaEnviron mental,Inc <br /> ! <br />