Appendix A - Site Background Information <br /> Former Stockton Plating Facility <br /> Page 6 of 7 <br /> the SVE network and to determine the SVE hydrocarbon destruction rate <br /> GROUND WATER EXTRACTION SYSTEM INSTALLATION <br /> Four 1 5-inch diameter, stainless steel QED Environmental model H23SET pneumatic powered, <br /> down-well pumps were installed in vapor extraction wells VW-1, VW-2, VW-3 and VW-4 The <br /> pumps were internally equipped with a one-way check valve to prevent back-flow The pumps were <br /> installed in each well at a depth of approximately 45 feet bsg One-half inch diameter poly-vinyl <br /> chloride (PVC)tubing was routed from each pump to the top of each well casing and through a 2- <br /> inch diameter sanitary well seal In the remediation area, a manifold was created with independent <br /> flow meters and a dedicated sampling port to allow sampling of each well independently without <br /> having to remove each respective well head assembly <br /> On 02 February 2004, a 4-inch diameter, stainless steel model 5 S 8 Grundfos Rediflow down-well <br /> pump equipped with 230 volt 1/2-horsepower 3-wire motors were installed in ground water extraction <br /> well EW-1 The Grundfos pump was Installed in well EW-1 at a depth of approximately 65 feet <br /> below surface grade(bsg) Schedule 40, 1-inch diameter PVC tubing was routed from the pump to <br /> the top of the well casing and through a 4-inch diameter sanitary well seal In the remediation area, <br /> an independent flow meter and a sampling port was Installed to allow sampling of the well without <br /> having to remove the well head assembly <br /> Installation of Ground Water Treatment System <br /> Three 2,000-gallon granular active carbon(GAC)media vessels,one 300-gallon poly tank(holding <br /> tank), one process pump and one sediment filter chamber were installed for the ground water <br /> treatment system <br /> Ground water pumped from the recovery wells is initially routed via the piping system to the 300- <br /> gallon poly tank(holding tank)prior to processing The holding tank is equipped with various water <br /> level float controls to control the rate at which extracted water is introduced into the treatment <br /> vessels, to allow coarser sediment to settle out prior to treatment and to provide safety shutoff <br /> capabilities A high float(high-high)was installed near the top of the holding tank and is designed <br /> to shut the entire system down if water level exceeds the high-high float A middle float (high- <br /> low)was installed near the middle of the holding tank and is designed to turn on the process pump <br /> when water level exceeds the high-low float A low float was installed near the bottom of the holding <br /> tank(low-low) and is designed to turn off the process pump <br /> • A '/2-horsepower, single-phase centrifugal process pump was installed inside the holding tank The <br /> Advanced GeoEnvironmental,Inc <br />