EXHIBIT "A" <br /> PHASING SCHEDULE <br /> PHASE I <br /> (TO BE COMPLETED BY DECEMBER, 1998) <br /> GRADE ALL ON-SITE GRADING AND INSTALL STORM DRAINAGE <br /> UNDERGROUND AND STORM DRAINAGE POND. <br /> INSTALL ALL FRONTAGE IMPROVEMENTS AND PAVE FIRST 75' OF DRIVEWAY, <br /> INSTALL WELL AND SEPTIC SYSTEM, PAVE PARKING AREA AND DRIVEWAY <br /> AROUND OFFICE, INSTALL 24'x50' MOBILE OFFICE (BUILDING "C") MOBILE <br /> OFFICE (BUILDING "C"), CONSTRUCT SHOP (BUILDING "B"), CONSTRUCT NH3 <br /> (AREA "D"), CONSTRUCTION LIQUID FERTILIZER (AREA (E), CONSTRUCT <br /> FLAMMABLE LIQUID AREA (AREA "F"), CONSTRUCT WASH AREA (AREA "G"), <br /> INSTALL AGGREGATE ROAD BASE ON ENTIRE SITE AND DRIVEWAY, EXCEPT <br /> EQUIPMENT STORAGE AREA. <br /> PHASE H <br /> (TO BE COMPLETED BY DECEMBER 2000) <br /> CONSTRUCT WAREHOUSE (BUILDING "A"), INSTALL SCALE (AREA "H"), <br /> INSTALL GRAVEL IN EQUIPMENT IN STORAGE AREA. <br /> INSTALL RAILROAD SPUR TRACK. <br /> PAVE REMAINING PORTION OF DRIVEWAY FROM OFFICE OUT TO JACK TONE <br /> ROAD. <br />