Laserfiche WebLink
EXHIBIT "A" <br /> PHASING SCHEDULE <br /> PHASE I <br /> (To be completed by May, 1998) <br /> Grade all on-site grading and install storm drainage underground and storm drainage pond. <br /> PHASE H <br /> (To be completed by May, 2000) <br /> Install all frontage improvements and pave first 75' of driveway, install well and septic <br /> system, pave parking area and driveway around office, install 24'x50' mobile office <br /> (Building "C"), construct shop (Building "B"), construct NH3 (Area "D"), construction liquid <br /> fertilizer (Area "E"), construct flammable liquid area (Area "F), construct wash area (Area <br /> "G"), install gravel on entire site and driveway, except equipment storage area. <br /> Equipment storage and agriculture service to begin. <br /> PHASE III <br /> (To be completed by May 2001) <br /> Construct warehouse (Building "A"), install scale (Area "H"), install gravel in equipment in <br /> storage area. <br /> PHASE IV <br /> (To be completed by May 2002) <br /> Pave remaining portion of driveway from office out to Jack Tone Road. <br />