Laserfiche WebLink
Biological Resources, MOND &ASSOCIATES <br /> Impacts and Mitigations <br /> Tracy Facility Expansion Site <br /> mined areas and reseeding this area with native grasses and forbs. The post excavation elevation <br /> in this area would be approximately 45-55 feet below existing grade. Final slope contours would <br /> be graded as shown in Appendix A,Figures 2 and 3. <br /> 5.3.2 CORRAL HOLLOW CREEK CROSSING <br /> To access the north side of Corral Hollow Creek a temporary crossing of this-creek would be <br /> installed at approximately station 2+00 during the first two years that the site is mined. With the <br /> exception of this creek crossing, the Corral Hollow Creek channel will be completely protected <br /> from all mining activities. The creek crossing would be approximately 30 feet wide and would <br /> consist of annual temporary installations of three parallel 48-inch diameter x 40-foot long <br /> corrugated steel culverts that would be covered with 3 feet of native material. These culverts <br /> would be installed no earlier that February 15th and removed no later than October 31St each <br /> year,but in no event would they be installed while the creek is flowing. These culverts would <br /> only carry unseasonal storm water flows in Corral Hollow Creek that occurred during the dry <br /> season. A streambed alteration agreement would be obtained from CDFG pursuant to Section <br /> 1603 of the Fish and Game Code prior to the installation of these.culverts. Similarly, verification <br /> for use of Nationwide Permit 14 (road crossings)would be obtained from the U.S. Army Corps <br /> of Engineers(Corps)prior to installation of these culverts. After mining and reclamation of the <br /> north portion of the project site, the road crossing would be permanently abandoned. <br /> 5.3.3 EXCAVATION OF THE SOUTH SITE <br /> Upon completion of mining activities north of Corral Hollow Creek, excavation of the portion of <br /> the site south of this creek would commence in the year 2001. All mining and reclamation <br /> activities would be completed over a 6-year period in accordance with the schedule presented in <br /> Table 1. The excavation depths south of Corral Hollow Creek would be variable and are i <br /> estimated to be from 10 to 80 vertical feet below the existing ground elevation. <br /> Excavation of the area south of Corral Hollow Creek would be similar to the north side of this <br /> creek. Since the existing grade elevation south of the creek is lower than north of the creek(due <br /> to previously mined conditions of this portion of the site and the general lay of the land), lean <br /> clays encountered during excavation would be used to construct a compacted clay berm along <br /> Corral Hollow Creek. This berm would be constructed to prohibit large storm event flows from <br /> entering into the southern mined area. Lean clays would also be used for final slope <br /> construction. <br /> Reclamation of the south side would include spreading previously stripped topsoil over the <br /> mined site. Mined areas would be re-seeded to native grasses and forbs and allowed to revert to <br /> an annual grassland habitat. All reclamation of the south site would be completed by the year <br /> 2006. <br /> 5 <br />