Laserfiche WebLink
Kennedy/Jenks Consultants <br /> Section 6: Implementation Schedule <br /> It is anticipated that the Work Plan will be implemented according to the following schedule: <br /> 12 November 2009 — Submit Work Plan to the CRWQCB. <br /> 15 January 2010 — Receive approval or comments from the CRWQCB. Submit <br /> encroachment and well installation permit applications. <br /> 8 February 2010 — Commence with drilling and monitoring well installation activities <br /> 15 February 2010 — Develop monitoring wells. <br /> 22 February 2010 — Collect groundwater samples. <br /> 8 March 2010 — Receive analytical results of groundwater samples. <br /> 17 June 2010 — Submit Hydrogeologic Investigation Report to the CRWQCB. <br /> Hydrogeologic Investigation and Groundwater Sampling and Analysis Work Plan, Page 17 <br /> Sutter Home Lodi Winery, Lodi, California <br /> g:K-9rwpd,+ pbW81066500506_5utterhomeW9repwts`wdr Ua WlddhydmwOfplwM.tda <br />