Kennedy/Jenks Consultants <br /> Section 6: implementation Schedule <br /> It is anticipated that the Work Plan will be implemented according to the following schedule, <br /> depending upon the availability of drilling subcontractors and San Joaquin County inspectors: — <br /> • 30 September 2013 — Submit Work Plan to the CRWQCB. <br /> • 14 October 2013 — Receive approval or comments from the CRWQCB. <br /> Submit well installation permit application. <br /> • 28 October 2013 — Initiate drilling and monitoring well installation activities. <br /> • 4 November 2013 — Develop monitoring wells. <br /> • 11 November 2013 — Collect groundwater samples. <br /> • 25 November 2013 — Receive analytical results of groundwater samples. <br /> • 3 January 2014 — Submit Report to the CRWQCB. <br /> Page 14 Monitoring Well Installation Work Plan <br /> Sutter Home Winery, Lodi, California — <br /> 9:�"mupl nnWbW9\096`5005.f 9_sutlftmeQgrt sM irtsW*WxtE .. <br />