Section 5.0 <br /> Project Schedule <br /> The overall investigation, soil removal, and backfill activities are expected to take 7 days. <br /> Activities will commence after the work plan has been approved by the Central Valley-Regional <br /> Water Quality Control Board. The hand-auger and groundwater sampling will be conducted <br /> approximately 3 days prior to the removal activities. The samples will be analyzed on a 24-hour <br /> turnaround basis. Analytical testing and the preparation of a final report will require <br /> approximately 30 calendar days for completion after receipt of analytical results. <br /> Rough&Ready Island 27 Tetra Tech, Inc. <br /> Revised Draft Work Plan November 18, 1998 <br />