Section 5 <br /> Schedule <br /> Installation of the monitoring wells could be completed by as early as the end of June,pending <br /> Regional Board review and approval of this workplan. Following well installation and <br /> development, a well survey and initial water samples will be collected. <br /> Table 5.1: Tentative Schedule of Well Completion (2006) <br /> Task Initiation Date Completion Date <br /> Regional Board Approval of Workplan May 5, 2006 June 2, 2006 <br /> Install Monitoring Wells June 5, 2006 June 30,2006 <br /> Initial Sampling July 3, 2006 July 31, 2006 <br /> Monitoring Well Installation Report n/a August 31,2006 <br /> May 2006 Main Stone Property <br /> 5-1 Effluent Storage and Disposal Site Hydrogeologic Investigation Workplan <br />