Laserfiche WebLink
Ford Construction <br /> VFF #1 Infection well <br /> Abandonment <br /> 2008 <br /> 4114 Move in KDY Rig # 1 and rig up, Found the well with Opsi tubing and 0 psi casing. Take on water, and <br /> pump 43 barrels of fresh water down 4.5" casing and pump down annulus, pressured up to 500psi_ Full. <br /> Remove production tree, Inspect tubing hanger, Install production tree. Secure rig. <br /> Daily cost:AM Cum cost: so <br /> 4/15 Remove Injection tree, Install 7 1/16", 5M BOP, nipple up and test to 2000psi. Unset packer, remove <br /> casing hanger, circulate, POOH laying down 4.5" casing ( 84 joints and 1 PIP Packer). Measure, Rabbit <br /> and pickup 2 3/8"4.7#, J-55, ELIE, Used tubing to 2972', tagged hard fill, attempt to circulate out.( EPA <br /> declared that would be deep enough to cement). Pull 5 stands and secure rig. <br /> Daily cost:IM Cum cost:WIi <br /> 4116 Rih and tag bottom (&2972', Circulate hole clean, Rig up MMI Cementers, Equalize 150 sacks of"G" <br /> Cement premixed with 2% CaC12, CIP @ 10:00, Pull up to 2000' and reverse circulate clean, pull 5 <br /> stands and Wait on Cement 4 hours. Rih, tag hard cement(a)2269', Circulate, Rig up MMI Cementers, <br /> Equalize 240 sacks of"G" Cement, premixed with 0.1% retarder(a� 2269'. Pull up to 950' and reverse <br /> circulate clean, Pull 5 stands and secure rig. <br /> Daily cost:400 Cum cost:~ <br /> 4/17 Rih and tag top of cement(& 1067'. POH laying down excess tubing, Rig up MMI Cementers and <br /> Equalize 191 sacks of"G" Cement, the first 50 sacks premixed with CAC12, the remaining 141 "G" <br /> cement @ 1067', POH laying down tubing. Wait 4 hours on cement, pickup 6 joints of tubing and tag top <br /> of cement @ 165 . Equalize 32 sacks of cement, pull out laying down tubing and fill hole with cement. <br /> Remove BOP, Rig down the rig, clean out washout pit and secure well <br /> Daily cost:400 Cum cost:Ow <br /> 4/18 Cut off wellhead, dig out cement on top of cellar and dig 5' below ground level, Found the cement 5' <br /> below, mix 2 sacks of cement and weld '/z' plate on 7" casing 5' below ground level, Back fill cellar, clean <br /> pit, prep to move. <br /> Daily cost: Cum cost: up <br /> 4121 Load out and move the rig to another location. <br /> Daily cost:dW Cum cost <br /> Sent 84 joints of 4.5", 10.50#, J-55, ST&C Used casing and packer to Ford Construction's yard <br /> Returned 150 joints of 2 3/8" Used tubing to Mike Cassel's yard. <br /> Injection tree and well head sent to Ford Construction's yard. <br />