Laserfiche WebLink
process. The water from th�tiell is used for the restroom. <br /> We discussed the timeline of the work near the ARCO property. I <br /> told Matt the area near ARCO is in phase IA of the project, which is the <br /> early stage. At present, the notice to proceed date is anticipated to <br /> be sometime in late November or early December, but exact dates are not <br /> yet fixed. He asked for more information on the exact details of the <br /> proposed roadway work. Adrienne has asked for this as well. I will <br /> get together with Ken Doty of the designer, Mark Thomas to coordinate. <br /> Meetings between the City, the CM, the Contractor, SJCEHD and <br /> representatives of the property owners should be held early to <br /> coordinate the efforts in these areas by all parties. <br /> I will keep all informed as to progress. <br /> Martin P. (Pat) Flatley, P.E. <br /> Supervising Bridge Construction Engineer <br /> Project Structures Representative <br /> Parsons Brinckerhoff Construction Services <br /> Cell Phone (925) 382-4507 <br /> 2 <br />