28 June 2001 <br /> AGE-NC Project No. 95-0103 <br /> Page 8 of 9 <br /> The PVC piping will be routed from each ground water extraction well head to a water holding tank; <br /> the holding tank will be connected to the GAC ground water treatment system; two in-line vessels. <br /> A plan of the proposed piping system and enclosed unit location are depicted in Figure 3. <br /> At the direction of the property owner and due to property use constraints,the location of the ground <br /> water pump and treat system is proposed to be at the southwest corner of the site(Figure 3). This <br /> proposed location of the pump and treat system will allow the site to conduct normal day-to-day <br /> business without interference from the operation of the remediation system. The pump and treat <br /> system will be secured by a chain-linked,gated enclosure will be approximately 12 feet wide,20 feet <br /> long and six feet high. <br /> Electricity is readily available to the site. A dedicated electrical meter has been installed that will <br /> connect directly to the pump and treat system. <br /> 4.4.2. Discharge Piping System <br /> AGE plans to install a two-inch diameter, schedule 40 polyvinylchloride (PVC)pipe underground <br /> along the west side of the site to the City of Stockton discharge line located in Buena Vista Avenue. <br /> (see Figure 3). AGE anticipates a continuous discharge of treated ground water from site to the City <br /> of Stockton sanitary sewer at a flow rate of approximately four to six gallons per minute. <br /> 4.4.3. Ground Water Extraction Monitoring Activities <br /> The pump and treat system will be monitored weekly to ensure optimal removal of dissolved <br /> petroleum hydrocarbons. The ground water influent and effluent flow readings will be recorded <br /> before the GAC filter-media phase. Grab treatment water samples will be collected on a monthly <br /> basis from the influent and effluent end of the pump and treat system. The water samples will be <br /> collected and transported to a DHS-certified laboratory, in a chilled container under ice, for water <br /> samples and under chain-of-custody procedure. <br /> During the "start-up" period for the ground water extraction system, operational parameters and <br /> ground water samples will be collected on a daily basis. The anticipated start-up period will be <br /> approximately two weeks.During the"start-up"period,five model 3001 Solinst Levelogger pressure <br /> transducers will be installed in the three new extraction and two additional shallow ground water <br /> monitoring wells. Weekly data will be collected from the ground water level transducers. <br /> Advanced GcoE nviron mental,Inc. <br />