Laserfiche WebLink
TABLE 4 <br /> COST ESTIMATE SUMMARY <br /> Item Unit Total <br /> No. Description Unit Qty Rate Cost <br /> 01 Mobilization/Demobilization 4,500.00 <br /> 02 Compliance of Health & Safety Plan 2,500.00 <br /> 03 Removal Action in Area A (see detailed descriptions) 11,325.00 <br /> 04 Removal Action in Area C (see detailed descriptions) 42,575.00 <br /> 05 Removal Action in Area J (see detailed descriptions) 35,805.00 <br /> Contractor Subtotal 96,705.00 <br /> A General and Administrative(15%) 14,505.00 <br /> Profit (10%) 9,670.00 <br /> Other Indirect Costs (5%) 4,835.00 <br /> Subtotal <br /> 125,715.00 <br /> Contingency (15%) 18,860.00 <br /> CONTRACTOR TOTAL COSTS 144,575.00 <br /> Oversight Costs (10%) 14,460.00 <br /> PROJECT TOTAL COST 159,035.00 <br />