June 14,1990 <br /> Thursday <br /> Day # 9 <br /> Safety Eric conducted the safety meeting See daily report <br /> for details <br /> Excavation Excavation of the east hole continues Sorting <br /> clean overburden from soil >lOK PPM Soil grater <br /> than 10K PPM is being moved to biocell <br /> Fill Drove to the quarry were fill material is to be <br /> Material obtained The quarry is large and located along a <br /> river off highway 4 the material is a silty sand <br /> Took a 5 gallon bucket sample to take to soil lab <br /> for a compaction curve analysis <br /> Followed Steve Steed of CKC to a possible source of <br /> soil This was on Hammer Lane near 99 on land being <br /> cleared and developed for commercial buildings <br /> Spoke with a geotech on site doing soils work for <br /> the developer He said that this soil would not <br /> make suitable fill material I had an additional <br /> concern that soil may have a pesticide <br /> contamination problem, this site is orchard lands <br /> Told Steve not to waste his time profiling this <br /> soil <br /> Visitors Jim and Jeff of D&M SAC office were on site to <br /> observe excavation and biocell progress <br /> Jim showed me were the electrical power must be <br /> located for the irrigation timer requested that I <br /> get a quote from local contractor for the <br /> installation work <br /> CKC Contract CKC signed the contract for their work <br /> June 15,1990 <br /> Friday <br /> Day # 10 <br /> Excavation West excavation completed Excavation was <br /> completed near the end of the day There was not <br /> enough time for soil sampling and have them to an <br /> analytical lab before closing Samples would be <br /> taken on monday morning and picked up by a <br /> Sacramento lab <br /> Biocell Cell is have constructed by end of day Having <br /> problems with gusty wind blowing up liner Place <br /> soil in small pills to hold liner in place until <br /> soil completely covers liner <br />