Laserfiche WebLink
June 22,1990 <br /> Friday <br /> Day # 15 <br /> Backfill AIM tested the sand backfill used in the bottom of <br /> the west excavation Results was 97% <br /> Sheepsfoot vibrator compaction equipment is <br /> delivered CKC has problem getting equipment into <br /> excavation, steep walls and small area at bottom of <br /> excavation are the cause of a one hour delay <br /> Sheepsfoot equipment breaks down causes two hour <br /> delay <br /> Biocell Fertilizer is delivered and spread over soil in <br /> main cell area using a hand held broadcasting piece <br /> of equipment by CKC <br /> Stockpile CKC continued to move stockpiled soil to the <br /> biocell area <br />