1 <br /> July 3,1990 <br /> Tuesday <br /> Day # 22 <br /> Backfill Backfilling continues Materials are slow in <br /> arriving on site from MR Trucker CKC said it was <br /> do to delay at the quarry <br /> t Backfill work is proceeding slowly because of the <br /> slow delivery of materials <br /> Storm Drains CKC ordered catch basin from supplier in Fremont <br />' Will have them picked up by CKC driver and <br /> delivered to site <br /> Dug catch basin holes and placed precast units with <br /> PVC pipe Did not complete work <br /> Will finish grout work to pipes on Monday <br />' Compaction Testing was rescheduled for Monday July 9th <br /> Testing They will be able to test final lift and base rock <br /> together <br /> Biocell Jim was on site with contractor from Sacramento to <br /> till the soil They had equipment problems till <br /> took longer than anticipated <br /> 1 <br /> 1 <br />