NOTES (Describe work completed during the day, any problems and their solutions): <br />Wood Brothers: 9 Man crew Surveyors Group Inc,: 2 Man crew D&E: 2 Man crew <br />Wood Bros. continued to moisture condition and compact subgrade material on the northern slope of module <br />1 utilizing the D5CXL, case tractor with scraper box, water truck and smooth drum roller. Wood Bros. <br />switched out smooth drum rollers. Wood Bros. continued to excavate the soil gas system trenches utilizing <br />Valley Trenching JS36 trencher. Wood Bros. had 5320' of 4" and 160' of 12" pipe SDR 15.5 delivered to the <br />site today. Wood Bros. had 8 loads of 3/8" pea gravel from Granites Tracy plant delivered to the site. Wood <br />Bros. placed geotextile, welded and placed the 4" slotted pipe with 2-3" of pea gravel under the pipe then <br />backfilled to within 1' of the finish grade with pea gravel wrapped in textile in the northern soil gas trench. <br />*Surveyors Group Inc: on site setting grade staking for the V ditches on the south side of Module 1, reset the <br />lysimeter staking, placed construction staking for the sump and started the 50' grid for finish grade on the <br />foundation layer. <br />D&E on site but no liner arrived on site today. <br />Vector Engineering, Inc. CQA observed processing, compaction and tested compaction of the subgrade <br />material on the northern slope of Module 1. CQA performed several density tests with all tests meeting the <br />required specifications. CQA observed unloading and logged all liner materials delivered to the site. CQA <br />observed unloading and logged pipe delivered to the site. <br />Vector discussed with Wood bros. Tony will get the office to fax the welders certificate to the trailer today. Trailer lost power today but it came <br />back on after the breaker switch was flipped back and forth. <br />File Name: Foothill Landfill Prepared By: Frank Dell -Era Reviewed B <br />Vector Engineering <br />Daily Field Report <br />Job Number: 031602.00 <br />Project Name: <br />Client Or Manager: <br />Daily Field Report Sequence Number. Days left in contract <br />Construction of 2 Landfill Modules- <br />County of San Joaquin <br />29 51 <br />Foothill Landfill <br />Location of Work: <br />Owner's Or Client's Representative <br />Date: <br />Day of The Week: <br />Stockton Ca. <br />Mike Carroll <br />7-29-03 <br />Tuesday <br />General Contractor. <br />Liner Contractor <br />Project Engineer. <br />Reviewed By: <br />Wood Brothers <br />D&E Construction <br />Bryan Fritzler <br />General Foreman: <br />Liner Superintendent: <br />Other <br />Tony Peichoto / Mario Garza <br />Eric Downs <br />Source and Description of Fill Material: <br />Weather. <br />CQA Technician: <br />On site Brown sandy silt <br />Clear Hot 1000 <br />Frank Dell -Era / Jeremy Freas <br />Equipment Utilized: <br />D5CXL Cat Dozer, Case Tractor with laser scraper box, Water Truck, Bomag Smooth Drum roller, Cleveland JS36 Trencher, John <br />Deere 21OLE skit) loader. <br />NOTES (Describe work completed during the day, any problems and their solutions): <br />Wood Brothers: 9 Man crew Surveyors Group Inc,: 2 Man crew D&E: 2 Man crew <br />Wood Bros. continued to moisture condition and compact subgrade material on the northern slope of module <br />1 utilizing the D5CXL, case tractor with scraper box, water truck and smooth drum roller. Wood Bros. <br />switched out smooth drum rollers. Wood Bros. continued to excavate the soil gas system trenches utilizing <br />Valley Trenching JS36 trencher. Wood Bros. had 5320' of 4" and 160' of 12" pipe SDR 15.5 delivered to the <br />site today. Wood Bros. had 8 loads of 3/8" pea gravel from Granites Tracy plant delivered to the site. Wood <br />Bros. placed geotextile, welded and placed the 4" slotted pipe with 2-3" of pea gravel under the pipe then <br />backfilled to within 1' of the finish grade with pea gravel wrapped in textile in the northern soil gas trench. <br />*Surveyors Group Inc: on site setting grade staking for the V ditches on the south side of Module 1, reset the <br />lysimeter staking, placed construction staking for the sump and started the 50' grid for finish grade on the <br />foundation layer. <br />D&E on site but no liner arrived on site today. <br />Vector Engineering, Inc. CQA observed processing, compaction and tested compaction of the subgrade <br />material on the northern slope of Module 1. CQA performed several density tests with all tests meeting the <br />required specifications. CQA observed unloading and logged all liner materials delivered to the site. CQA <br />observed unloading and logged pipe delivered to the site. <br />Vector discussed with Wood bros. Tony will get the office to fax the welders certificate to the trailer today. Trailer lost power today but it came <br />back on after the breaker switch was flipped back and forth. <br />File Name: Foothill Landfill Prepared By: Frank Dell -Era Reviewed B <br />