Vector Engineering <br />Daily Field Report <br />Job Number: 031602.00 <br />Project Name: <br />Client Or Manager. <br />Daily Field Report Sequence Number. Days left in contract <br />Construction of 2 Landfill Modules- <br />County of San Joaquin <br />33 47 <br />Foothill Landfill <br />Location of Work: <br />Owner's Or Client's Representative <br />Date: <br />Day of The Week: <br />Stockton Ca. <br />Mike Carroll <br />8-4-03 <br />Monday <br />General Contractor. <br />Liner Contractor: <br />Project Engineer: <br />Reviewed By: <br />Wood Brothers <br />D&E Construction <br />Bryan Fritzler <br />General Foreman: <br />Liner Superintendent: <br />Other. <br />Tony Peichoto / Mario Garza <br />Eric Downs <br />Source and Description of Fill Material: <br />Weather. <br />CQA Technician: <br />On site Brown sandy silt <br />Clear Warm 850 <br />Frank Dell -Era <br />Equipment Utilized: <br />D5CXL Cat Dozer, Case Tractor with laser scraper box, Water Truck, Bomag Smooth Drum roller, Cleveland JS36 Trencher, John <br />Deere 210LE ski loader, 310SE John Deere Backhoe, 140 cat grader, 853H Bobcat, Acker drill rig. <br />NOTES (Describe work completed during the day, any problems and their solutions): <br />Wood Brothers: 13 Man crew Krazan: 5 Man Crew Industrial Fence: 2 Man crew <br />D&E: 1 Man crew <br />Wood Bros. moisture conditioned and compacted foundation layer material in the sump utilizing the <br />D5CXL, case tractor with scraper box, water truck, 825 sheepsfoot compactor and smooth drum roller. <br />Wood Bros. continued to excavate the soil gas system trenches along the eastern and western toe of slope <br />utilizing Valley Trenching JS36 trencher. Wood Bros. continued to place geotextile, weld and place the 4" <br />slotted pipe with 2-3" of pea gravel under the pipe then backfilled to within V of the finish grade utilizing <br />the skip loader and the backhoe in the northern and eastern soil gas trench. Wood Bros. had 7 loads of 3/8" <br />+pea gravel from Granites Tracy plant delivered to the site. Wood Bros. utilized the Case tractor to remove <br />sandy material from the southern slope and replace with some silty material for a more stable subgrade and <br />easier compaction. Wood Bros. excavated the lysimeter trench for LZ#2 utilizing the John Deere backhoe. <br />Industrial fence augured fencepost holes for the eastern fence utilizing the Bobcat with auger. <br />Krazan drilled Lysimeters 1-4. Krazan installed Lysieters LZ#1 / LZ#4. No inspector from the County was <br />available as due to strike. <br />D&E unloaded 1 load of geocomposite liner material totaling approximately 46,400$2 today. <br />Vector Engineering, Inc. CQA observed processing, compaction and tested compaction of the foundation <br />layer material placed in the sump area. CQA performed several density tests with all tests meeting the <br />required specifications. CQA observed pipe welding, geotextile placement and backfill of the soil gas system <br />with 3/8" pea gravel. CQA observed excavation of the Lysimeter trench in sump. CQA observed drilling and <br />installation of lysimeter #4. CQA observed and logged liner materials delivered to the site. <br />Vector discussed with Wood bros. will continue placement of gravel, welding of pipe and excavation of the soil gas trenches. Wood bros. will <br />MC% and compact the sump area today and Industrial fence will be on site to start the eastern fence. Krazan will be on site today for the <br />lysimeter installation. CQA discussed with Tony of Wood Bros. when they where going to finish grading the north slope tony said that the grader <br />would not stay on the slope. Drilling the postholes is slow due to hard pan <br />File Name: Foothill Landfill Prepared By: Frank Dell -Era Reviewed By: <br />