Vector Engineering <br />Daily Field Report <br />Job Number: 031602 00 <br />Project Name: <br />Client Or Manager. <br />Daily Field Report Sequence Number. Days left in cont <br />Construction of 2 Landfill Modules- <br />County of San Joaquin <br />50 30 <br />Foothill Landfill <br />Location of Work: <br />Owner's Or Client's Representative <br />Date: <br />Day of The Week: <br />Stockton Ca. <br />Mike Carroll <br />8-27-03 <br />Wednesday <br />General Contractor. <br />Liner Contractor <br />Project Engineer: <br />- <br />Reviewed By: <br />Wood Brothers <br />D&E Construction <br />Bryan Fritzler <br />General Foreman: <br />Liner Superintendent: <br />Other. <br />Tony Peichoto / Mario Garza <br />Eric Downs/ <br />Source and Description of Fill Material: <br />Weather. <br />CQA Technician: <br />On site Brown sandy silt <br />Rnninm IT*;[-' ed <br />Clear 940 <br />Frank Dell -Era / Ham Munster <br />Water Truck, Ingersol Rand Smooth Drum roller 140 cat grader, TH83 Cat Forklift, 227 Cat Track forklift. <br />NOTES (Describe work completed during the day, any problems and their solutions): <br />Wood Brothers: 5 Man crew D&E: 12 Man crew <br />Wood Bros. continued import of Drainage aggregate for the LCRS system. Wood bros continued to utilize <br />the D5CXL dozer to spread the material onto the cell floor. <br />D&E: Prior to panel placement D&E utilized the smooth drum to roll the subgrade in contact with the GCL <br />materials. D&E continued installation of GCL rolls with a minimum of 351bs peel and 60mi1 double textured <br />liner. D&E continued to deploy on the floor of Module 1. D&E installed a total of 35 panels of GCL totaling <br />approximately 72,712.5$2 and 11 panels of geomembrane totaling approximately 89,335ft2 all panels were <br />overlapped and seamed per specifications. D&E placed sandbags as ballast on the liner edges prior to leaving <br />the site. 40 <br />Vector Engineering, Inc. CQA observed placement of the LCRS drainage aggregate. CQA pulled sieve <br />analysis samples and shipped 4 buckets of LCRS proposed drainage aggregate to Vector Engineering for <br />testing. CQA observed and logged subgrade acceptance, panel deployment, seaming, airtests performed on <br />the liner materials. CQA marked destructive samples on the liner material placed. CQA pulled 2 samples for <br />sieve analysis and plasticity Index testing of proposed operations material. <br />Vector discussed with Wood bros. continue import and placement of LCRS gravel. CQA observed the drainage aggregate looked dirty and asked <br />Tony with wood brothers to call and make sure it was washed materials. Tony called Granites pit boss whom assured Tony it was washed. D&E <br />will continue GCL and liner deployment on the floor in Module 1. <br />0 <br />File Name: Foothill Landfill Prepared By: Frank Dell -Era Reviewed By: <br />