v <br />C <br />Vector Engineering <br />Daily Field Report <br />Project Name: <br />Construction of 2 Landfill Modules- <br />Foothill Landfill <br />Client Or Manager.. V✓LVV` Vy <br />County of San Joaquin <br />Daily Field Report Sequence Number. Days left in contract <br />79 1 <br />Location of Work: <br />Stockton Ca. <br />Owner's Or Client's Representative <br />Date: Day of The Week: <br />Mike Carroll <br />10-08-03 Wednesday <br />General Contractor. <br />Wood Brothers <br />Liner Contractor. <br />D&E Construction <br />Project Engineer. Reviewed By: <br />Bryan Fritzler <br />General Foreman: <br />Liner Superintendent: <br />Other. <br />Mark Ceohlo <br />Eric Downs/Victor Cassilas <br />Source and Description of Fill Material: <br />Weather <br />CQA Technician: <br />Brown sand silt <br />Clear 940Frank <br />Dell -Era / Nathan DeWitt <br />Eauinment Utilized <br />Water Truck, 2-D6LGP Cat Dozers, 2-623 Cat Paddle wheel scrapers, TH83 Cat Forklift, 227 Cat Track forklift <br />NOTES (Describe work completed during the day, any problems and their solutions): <br />Wood Brothers: 9 Man crew D&E: 12 Man crew <br />Wood Bros. continued to import drainage aggregate material from Granites Tracy plant utilizing 15 transfer <br />and end dump trucks. Wood bros continued to grade the Drainage aggregate for the LCRS system utilizing <br />the D6LGP with a laser set-up and a laborer watching for wrinkles. Wood Bros continued placement of <br />operations on the northwest portion of Module 1 utilizing two 623 paddle wheel scrapers and a D6LGP with <br />a laborer to spread the material. <br />D&E completed installation of GCL and liner in Module 1. D&E installed a total of 38 panels of GCL <br />totaling approximately 31,247ft2 and 13 panels of geoembrane totaling approximately 29,362ft2 all panels <br />were overlapped and seamed per specifications. D&E performed repairs and air tested seams. D&E <br />performed repairs to sewn geotextile seams CQA had marked. <br />Vector Engineering, Inc. CQA observed placement and grading of the LCRS drainage aggregate imported <br />today. CQA observed and logged subgrade acceptance, panel deployment, start-up's, seaming, air tests and <br />repairs on the liner materials. CQA marked destructive samples. <br />Vector discussed with Wood Bros. start time for next week. 6:30. <br />File Name: Foothill Landfill Prepared B : Frank Dell -Era Reviewed By: <br />