As-Built CQA Report for the Construction of Area 2A at the Foothill Sanitary Landfill <br /> San Joaquin County,California <br /> 3.0 SOIL GAS COLLECTION PIPE AND LYSIMETER <br /> 3.1 GENERAL <br /> A soil gas collection pipe and a lysimeter were constructed below the grade of the Area 2A <br /> composite liner system. These features,installed to provide a means to control gas and monitor the <br /> vadose zone, included geomembrane, geotextile, gravels, Controlled-Low Strength Material (CLSM), <br /> and piping required for monitoring and testing in accordance with the CQA Manual. <br /> 3.2 SOIL GAS COLLECTION PIPE <br /> The Soil Gas Collection Pipe system beneath the floor of Area 2A included a trench consisting of <br /> perforated 4-inch HDPE pipe (SDR 11) surrounded by GDM and encased by 8-oz non-woven filter <br /> geotextile. The soil gas system details are shown on Sheets C-2 and C-6 of the Construction <br /> Drawings, which are included in Appendix D.1. The perforated soil gas collection pipe and gravel <br /> section was terminated at the toe of the eastern slope. A solid riser pipe was extended from the <br /> termination of the perforated section to a surface completion at the top of the eastern slope. The <br /> trench with the solid riser pipe section was backfilled with CLSM,a mixture of sand and cement. <br /> A CAT 320 excavator was used to excavate the soil gas trench across the floor and up the eastern <br /> slope. The excavation was performed through placed foundation layer soil. The excavation on the <br /> floor was staged to separate the upper 1 foot of foundation layer soil from underlying native <br /> materials. Along the floor, laborers installed 8-oz geotextile and fusion welded perforated HDPE <br /> pipe. A CAT 430 backhoe was used to haul and place GDM around the perforated pipe up to the <br /> grade of the base of the foundation layer soil. The excavated foundation layer soils were moisture <br /> conditioned and used to backfill and compact the upper portion of the trench using a vibratory <br /> plate compactor. Laborers also installed and fusion welded the solid riser section up the eastern <br /> slope. The riser trench was backfilled with 16 cubic yards of CLSM to complete the installation. <br /> The CQA activities during installation of the soil gas collection pipe included: <br /> ■ Review of MQC data and conformance tests of 8-oz geotextile. <br /> ■ Sampling and gradation testing of LCRS granular drainage material. <br /> ■ Observation of fusion welding of perforated and solid sections of HDPE pipe. <br /> ■ Observation during trenching and placement of geotextile, piping and GDM in perforated <br /> sections. <br /> ■ In-place density testing of foundation layer soil backfilled over the soil gas collection pipe on <br /> the floor. <br /> PA14 Projects114-101(SJCDPW North County and Foothill)IFoothill CQA1Report\Final ReportToothill CQA Rport-Final.docx <br /> P011 <br />