Laserfiche WebLink
Action <br />1 Submit WMU B Partial Final Closure Plan <br />2 Construct WMU D-00, Stockpile Soils <br />3 Flatten South Slope of WMU B to 2H:1V <br />4 Construct WMU D-01, Stockpile Soils <br />5 WMU B Filling Area Reaches Capacity; <br />Start 5 -year Settlement Period <br />6 Construct WMU D-02, Stockpile Soils <br />7 Re-evaluate Need for Landfill Gas Collection <br />and Control System in WMU B Area <br />8 Submit WMU B Final Closure Construction <br />Drawings and Specifications <br />9 Select WMU B Final Closure Contractor <br />10 Initiate Closure Construction Activities <br />11 Complete Closure Construction Activities <br />12 Submit WMU B Final Closure COA Report <br />nAallied waste\forward\misc\ws0264-time.vsd 9/22/99 <br />PROJECT SCHEDULE <br />WMU B Closure <br />Forward Landfill <br />Manteca, California <br />Approximate Date <br />1999 2000 2001 2002 2003 2004 2005 2006 <br />LEWIS r <br />Forward, Inc. ENGINEERING GeoSyntec Consultants <br />LEGEND <br />Scheduled Action <br />